Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T14CM03366
Permit Details
Apply Date:
06/04/2014
Applicant:
JAMES FARRELL
Description:
MEDICAL FACILITY
Architects:
- CURTIS, D DUSTIN
Contractors:
- MARKET CONTRACTORS LTD
Permit Reviews
Permit Number - T14CM03366
Permit Status: C of o
Permit Description: MEDICAL FACILITY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/04/2014 | COMMERCIAL - TI | 06/04/2014 | COMPLETED |
06/04/2014 | COMMERCIAL - TI | 07/03/2014 | COMPLETED |
07/17/2014 | RESUBMITTAL | 08/12/2014 | COMPLETED |
08/12/2014 | RESUBMITTAL | 08/15/2014 | COMPLETED |
08/15/2014 | RESUBMITTAL | 09/15/2014 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T14CM03366
Permit Status: C of o
Permit Description: MEDICAL FACILITY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/04/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T14CM03366
Permit Description: MEDICAL FACILITY
Total Completed Inspections - 32
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/08/2014 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
10/08/2014 | ELECTRIC - UNDERGROUND | BBENEDON | Approved | IVRS - Inspection :* |
11/20/2014 | MECHANICAL - INTERMEDIATE | JMILITELLO | Approved | CHECKED FIRE DAMPER OPENINGS OK TO PROCEED OK TO TAPE WALLS IN WATER TREATMENT ROOM OK TO TAPE ONE SIDE WALLS OK FOR SHEET ROCK OUTSIDE WALLS OF WATER TREATMENT |
11/20/2014 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
11/25/2014 | SHEET ROCK NAILING | JMILITEL | Approved | IVRS - Inspection :* |
12/03/2014 | PLUMBING - PROGRESS | JMILITELLO | Approved | PROVIDE HAMMER ARRESTORS AT BED PAN WASH. OK TO COVER WALL AT ENTRY. OK TO INSULATE WATER PIPING ALL TO EASTSIDE VALVES |
12/03/2014 | PLUMBING - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
12/05/2014 | PLUMBING - GAS PRESSURE TEST | JMILITEL | Approved | IVRS - Inspection :* |
12/08/2014 | GAS CLEARANCE | JMILITELLO | Approved | |
12/11/2014 | FRAMING | JMILITELLO | Approved | OK TO SHEETROCK WALLS & CEILINGS AT ENTRY AND RESTROOMS AT ENTRY |
12/11/2014 | FRAMING | JMILITEL | Approved | IVRS - Inspection :* |
12/15/2014 | ELECTRIC - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
12/16/2014 | BUILDING - PROGRESS | JMILITELLO | Approved | KICKERS OK. OK TO SHEETROCK HARD LIDS WITH SURFACE MOUNT LIGHTS. OK FOR PARTIAL CEILING TILES IN WATER TREATMENT ROOM |
12/16/2014 | TEP CLEARANCE - AM | jmilitello | Approved | recn |
12/16/2014 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
12/16/2014 | PLUMBING - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
12/16/2014 | ELECTRIC - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
12/16/2014 | BUILDING - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
01/21/2015 | ELECTRIC - UFER | JMILITEL | Approved | IVRS - Inspection :* |
01/21/2015 | PLUMBING - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
01/21/2015 | ELECTRIC - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
02/25/2015 | BUILDING ABOVE CEILING | JMILITELLO | Approved | BOND BUILDING GAS PIPING. FIX ALL PLUMBING LEAKS & PAINT EXPOSED PVC. FLUSH HANDLE ON ONE CLOSET WRONG SIDE. PROVIDE APPROVED BUSHINGS @ A/C UNITS. PROVIDE THE PROPER SIZE ROOF CURB AT EF7. SECURE EF5. PROVIDE VACUUM BREAKERS @ EXTERIOR HOSE BIBS. FINISH CONNECTING SINKS @ TREATMENT AREA. STERILIZATION REPORT, AIR BALANCE REPORT, & BACKFLOW CERTIFICATION ARE OK |
02/25/2015 | PLUMBING - GAS PRESS TEST FNL | JMILITEL | Approved | IVRS - Inspection :* |
02/25/2015 | BUILDING ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
02/26/2015 | ELECTRIC - TEMP POWER FOR TEST | JMILITELLO | Approved | PER ELEC FINAL |
02/26/2015 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
02/26/2015 | PLUMBING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
02/26/2015 | ELECTRIC - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
02/27/2015 | FIRE - FINAL | CBASALDUA | Approved | |
02/27/2015 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
02/27/2015 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
03/06/2015 | BUILDING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |