Inspection Status: Approved
Inspection History: BUILDING ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 02/25/2015 |
BUILDING ABOVE CEILING |
|
Approved |
IVRS - Inspection :* |
| 02/25/2015 |
BUILDING ABOVE CEILING |
|
Approved |
BOND BUILDING GAS PIPING. FIX ALL PLUMBING LEAKS & PAINT EXPOSED PVC. FLUSH HANDLE ON ONE CLOSET WRONG SIDE. PROVIDE APPROVED BUSHINGS @ A/C UNITS. PROVIDE THE PROPER SIZE ROOF CURB AT EF7. SECURE EF5. PROVIDE VACUUM BREAKERS @ EXTERIOR HOSE BIBS. FINISH CONNECTING SINKS @ TREATMENT AREA. STERILIZATION REPORT, AIR BALANCE REPORT, & BACKFLOW CERTIFICATION ARE OK |
| 01/20/2015 |
BUILDING ABOVE CEILING |
|
Partial Approval |
IVRS - Inspection :* |