Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
837 W IRVINGTON RD
Apply Date:
02/20/2014
Applicant:
CORY WIEBERS
Description:
NEW CAR WASH
Contractors:
  • BARKER MORRISSEY CONTRACTING INC **APA**

Permit Reviews

Permit Number - T14CM01004
Permit Status: C of o
Permit Description: NEW CAR WASH
Start Date Submittal Complete Date Status  
02/20/2014 PLANS OK TO SUBMIT - COMM 02/20/2014 COMPLETED Review Details
02/20/2014 COMMERCIAL - NEW 03/28/2014 COMPLETED Review Details
05/01/2014 RESUBMITTAL - TI ALL 05/16/2014 COMPLETED Review Details
06/02/2014 RESUBMITTAL - TI ALL 07/07/2014 COMPLETED Review Details
07/07/2014 RESUBMITTAL 08/25/2014 COMPLETED Review Details
09/18/2014 REVISION - - 1ST 09/18/2014 ACTIVE Review Details

Outstanding Activity Conditions

Permit Number - T14CM01004
Permit Status: C of o
Permit Description: NEW CAR WASH
Total Outstanding Activity Conditions - 1
Date Name
02/20/2014 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T14CM01004
Permit Description: NEW CAR WASH
Total Completed Inspections - 43
Date Description Inspector Results Comments
10/07/2014 ELECTRIC - CONSTRUCTION POWER DSANTACR Approved IVRS - Inspection :*
10/08/2014 TEP CLEARANCE - AM DSANTACRUZ Approved TMPP
11/20/2014 ELECTRIC - UNDERGROUND RCANCINO Approved OK TO BURY UG CONDUIT FROM J-30 TO INSIDE WALL
12/09/2014 EXCAVATION/LAYOUT REBAR & ZON RCAMACHO Approved RETURN INSPECTION. NORTH WFI WALL PER DETAIL 102 NE WF3 & NW WF3 FOOTERS. WF4 FOOTER. WF2 FOOTER PER DETAIL 103
12/09/2014 EXCAVATION/LAYOUT REBAR & ZON RCAMACHO Approved IVRS - Inspection :*
12/22/2014 STEM WALL/RETAINING WALL RCAMACHO Approved 1. PER DETAILS 102 & 103 NORTH TUNNEL WALL ONLY STEM
2. 12' LIFT SOUTH TUNNEL WALL ONLY
12/22/2014 STEM WALL/RETAINING WALL RCAMACHO Approved IVRS - Inspection :*
12/31/2014 REINFORCED MASONRY PRE-GROUT RCAMACHO Approved 1. NORTH TUNNEL WALL 12' LIFT ONLY
2. WF4 & WF2 WALLS 12' HEIGHT ONLY
3. SW TUNNEL WALL 12' HEIGHT ONLY
12/31/2014 REINFORCED MASONRY PRE-GROUT RCAMACHO Approved IVRS - Inspection :*
02/02/2015 PLUMBING - YARD WTR LINE/TEST RCAMACHO Approved IVRS - Inspection :*
02/06/2015 BUILDING PRE-SLAB RCANCINO Approved THIS COMPLETES ALL BUILDINGS PRE-SLAB
02/18/2015 ELECTRIC - UFER RCAMACHO Approved IVRS - Inspection :*
02/23/2015 ROOF NAILING RCANCINO Approved THIS INSPECTION DONE AS AN AFTER HOURS INSPECTION
02/23/2015 SITE - SEWER RCANCINO Approved IVRS - Inspection :*
02/23/2015 ROOF NAILING RCANCINO Approved IVRS - Inspection :*
03/06/2015 PLUMBING - ROOF DRAINS RCANCINO Approved IVRS - Inspection :*
03/06/2015 STUCCO MESH RCANCINO Approved IVRS - Inspection :*
03/06/2015 FRAMING RCANCINO Approved IVRS - Inspection :*
03/17/2015 U VALUE FOR WINDOW RCANCINO Approved IVRS - Inspection :*
04/01/2015 MECHANICAL - ABOVE CEILING RCANCINO Approved IVRS - Inspection :*
04/01/2015 PLUMBING - ABOVE CEILING RCANCINO Approved IVRS - Inspection :*
04/01/2015 ELECTRIC - CABLE DROP RCANCINO Approved IVRS - Inspection :*
04/01/2015 ELECTRIC - ABOVE CEILING RCANCINO Approved IVRS - Inspection :*
04/01/2015 BUILDING ABOVE CEILING RCANCINO Approved IVRS - Inspection :*
04/14/2015 MECHANICAL - INTERMEDIATE RCANCINO Approved IVRS - Inspection :*
04/14/2015 PLUMBING - INTERMEDIATE RCANCINO Approved IVRS - Inspection :*
04/21/2015 PLUMBING - PROGRESS RCANCINO Approved IVRS - Inspection :*
04/21/2015 PLUMBING - ROUGH, SOIL RCANCINO Approved IVRS - Inspection :*
04/21/2015 BUILDING - PROGRESS RCANCINO Approved IVRS - Inspection :*
05/08/2015 PLUMBING - PRE SLAB rcancino Approved
05/08/2015 ELECTRIC - INTERMEDIATE rcancino Approved
05/08/2015 MECHANICAL - FINAL RCANCINO Approved IVRS - Inspection :*
05/08/2015 PLUMBING - FINAL RCANCINO Approved IVRS - Inspection :*
05/08/2015 ELECTRIC - FINAL RCANCINO Approved IVRS - Inspection :*
05/08/2015 ELECTRIC - OUTDOOR LIGHTING RCANCINO Approved IVRS - Inspection :*
05/08/2015 FIRE - FINAL kenb Approved
05/12/2015 NPPO - FINAL RLEDONNE Approved
05/12/2015 SIGN - FINAL RLEDONNE Approved
05/12/2015 LANDSCAPE - FINAL RLEDONNE Approved
05/13/2015 RIGHT OF WAY - FINAL JC Approved
05/13/2015 RIGHT OF WAY - FINAL JC Approved
05/14/2015 ENGINEERING - FINAL DROBERTS Approved
06/03/2015 BUILDING - FINAL RCANCINO Approved