Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/14/2015 | ENGINEERING - FINAL | Approved | ||
| 05/12/2015 | ENGINEERING - FINAL | Continued | ||
| 05/08/2015 | ENGINEERING - FINAL | Not ready for Inspection | SITE IS NOT COMPLETE AT THIS TIME, THE CONTRACTTOR WILL BE WORKING ON THE MISSING ITEMS AND SHOULD BE READY FOR ANOTHER INSPECTION BY 5/15/2015. I WILL ASK RON TO CHECK THIS SITE ONCE HE RETURNS ON TUESDAY FOR A FULL SIGN OFF OF THE PLANS. I HAVE ADVISED THE OWNERS REPRESENTATIVES THAT HE HAS AN ILLEGAL ELECTRONICAL MESSAGE SIGN ON SITE DUE TO THE FACT THAT THE MESSAGE IS CHANGING MORE THAN ONCE AN HOUR. HE WILL CHECK WITH HIS SIGN CONTRACTOR AND HAVE THE NECESSARY CHANGES MADE TO THIS SIGN PRIOR TO CALLING FOR THE FINAL OF THE SITE. |
|
| 04/16/2015 | ENGINEERING - FINAL | Not ready for Inspection | CROSS SLOPES ON EAST END OF SIDE WALK OVER 2% | |
| 04/14/2015 | ENGINEERING - FINAL | Not ready for Inspection | CREWS ARE WORKING AROUND THE SITE TRYING TO COMPLETE SOME OF THE AREAS AND PLACE BACKFILL MATERIAL AROUND THE SITE AS NEEDED. |