Permit: T14CM01004
Permit Details
Apply Date:
02/20/2014
Applicant:
CORY WIEBERS
Description:
NEW CAR WASH
Contractors:
- BARKER MORRISSEY CONTRACTING INC **APA**
Permit Reviews
Permit Number - T14CM01004
Permit Status: C of o
Permit Description: NEW CAR WASH
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/20/2014 | PLANS OK TO SUBMIT - COMM | 02/20/2014 | COMPLETED |
| 02/20/2014 | COMMERCIAL - NEW | 03/28/2014 | COMPLETED |
| 05/01/2014 | RESUBMITTAL - TI ALL | 05/16/2014 | COMPLETED |
| 06/02/2014 | RESUBMITTAL - TI ALL | 07/07/2014 | COMPLETED |
| 07/07/2014 | RESUBMITTAL | 08/25/2014 | COMPLETED |
| 09/18/2014 | REVISION - - 1ST | 09/18/2014 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T14CM01004
Permit Status: C of o
Permit Description: NEW CAR WASH
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/20/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T14CM01004
Permit Description: NEW CAR WASH
Total Completed Inspections - 43
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/07/2014 | ELECTRIC - CONSTRUCTION POWER | DSANTACR | Approved | IVRS - Inspection :* |
| 10/08/2014 | TEP CLEARANCE - AM | DSANTACRUZ | Approved | TMPP |
| 11/20/2014 | ELECTRIC - UNDERGROUND | RCANCINO | Approved | OK TO BURY UG CONDUIT FROM J-30 TO INSIDE WALL |
| 12/09/2014 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | RETURN INSPECTION. NORTH WFI WALL PER DETAIL 102 NE WF3 & NW WF3 FOOTERS. WF4 FOOTER. WF2 FOOTER PER DETAIL 103 |
| 12/09/2014 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | IVRS - Inspection :* |
| 12/22/2014 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | 1. PER DETAILS 102 & 103 NORTH TUNNEL WALL ONLY STEM 2. 12' LIFT SOUTH TUNNEL WALL ONLY |
| 12/22/2014 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | IVRS - Inspection :* |
| 12/31/2014 | REINFORCED MASONRY PRE-GROUT | RCAMACHO | Approved | 1. NORTH TUNNEL WALL 12' LIFT ONLY 2. WF4 & WF2 WALLS 12' HEIGHT ONLY 3. SW TUNNEL WALL 12' HEIGHT ONLY |
| 12/31/2014 | REINFORCED MASONRY PRE-GROUT | RCAMACHO | Approved | IVRS - Inspection :* |
| 02/02/2015 | PLUMBING - YARD WTR LINE/TEST | RCAMACHO | Approved | IVRS - Inspection :* |
| 02/06/2015 | BUILDING PRE-SLAB | RCANCINO | Approved | THIS COMPLETES ALL BUILDINGS PRE-SLAB |
| 02/18/2015 | ELECTRIC - UFER | RCAMACHO | Approved | IVRS - Inspection :* |
| 02/23/2015 | ROOF NAILING | RCANCINO | Approved | THIS INSPECTION DONE AS AN AFTER HOURS INSPECTION |
| 02/23/2015 | SITE - SEWER | RCANCINO | Approved | IVRS - Inspection :* |
| 02/23/2015 | ROOF NAILING | RCANCINO | Approved | IVRS - Inspection :* |
| 03/06/2015 | PLUMBING - ROOF DRAINS | RCANCINO | Approved | IVRS - Inspection :* |
| 03/06/2015 | STUCCO MESH | RCANCINO | Approved | IVRS - Inspection :* |
| 03/06/2015 | FRAMING | RCANCINO | Approved | IVRS - Inspection :* |
| 03/17/2015 | U VALUE FOR WINDOW | RCANCINO | Approved | IVRS - Inspection :* |
| 04/01/2015 | MECHANICAL - ABOVE CEILING | RCANCINO | Approved | IVRS - Inspection :* |
| 04/01/2015 | PLUMBING - ABOVE CEILING | RCANCINO | Approved | IVRS - Inspection :* |
| 04/01/2015 | ELECTRIC - CABLE DROP | RCANCINO | Approved | IVRS - Inspection :* |
| 04/01/2015 | ELECTRIC - ABOVE CEILING | RCANCINO | Approved | IVRS - Inspection :* |
| 04/01/2015 | BUILDING ABOVE CEILING | RCANCINO | Approved | IVRS - Inspection :* |
| 04/14/2015 | MECHANICAL - INTERMEDIATE | RCANCINO | Approved | IVRS - Inspection :* |
| 04/14/2015 | PLUMBING - INTERMEDIATE | RCANCINO | Approved | IVRS - Inspection :* |
| 04/21/2015 | PLUMBING - PROGRESS | RCANCINO | Approved | IVRS - Inspection :* |
| 04/21/2015 | PLUMBING - ROUGH, SOIL | RCANCINO | Approved | IVRS - Inspection :* |
| 04/21/2015 | BUILDING - PROGRESS | RCANCINO | Approved | IVRS - Inspection :* |
| 05/08/2015 | PLUMBING - PRE SLAB | rcancino | Approved | |
| 05/08/2015 | ELECTRIC - INTERMEDIATE | rcancino | Approved | |
| 05/08/2015 | MECHANICAL - FINAL | RCANCINO | Approved | IVRS - Inspection :* |
| 05/08/2015 | PLUMBING - FINAL | RCANCINO | Approved | IVRS - Inspection :* |
| 05/08/2015 | ELECTRIC - FINAL | RCANCINO | Approved | IVRS - Inspection :* |
| 05/08/2015 | ELECTRIC - OUTDOOR LIGHTING | RCANCINO | Approved | IVRS - Inspection :* |
| 05/08/2015 | FIRE - FINAL | kenb | Approved | |
| 05/12/2015 | NPPO - FINAL | RLEDONNE | Approved | |
| 05/12/2015 | SIGN - FINAL | RLEDONNE | Approved | |
| 05/12/2015 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 05/13/2015 | RIGHT OF WAY - FINAL | JC | Approved | |
| 05/13/2015 | RIGHT OF WAY - FINAL | JC | Approved | |
| 05/14/2015 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 06/03/2015 | BUILDING - FINAL | RCANCINO | Approved |