Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T14CM00889
Permit Details
Apply Date:
02/14/2014
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW RETAIL BUILDING
Contractors:
- BARKER MORRISSEY CONTRACTING INC **APA**
Permit Reviews
Permit Number - T14CM00889
Permit Status: C of o
Permit Description: NEW RETAIL BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/14/2014 | PLANS OK TO SUBMIT - COMM | 02/14/2014 | COMPLETED |
02/14/2014 | COMMERCIAL - NEW | 03/14/2014 | COMPLETED |
03/14/2014 | RESUBMITTAL - TI ALL | 03/27/2014 | COMPLETED |
03/27/2014 | RESUBMITTAL | 03/28/2014 | COMPLETED |
05/12/2014 | REVISION - - 1ST | 05/12/2014 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T14CM00889
Permit Status: C of o
Permit Description: NEW RETAIL BUILDING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/14/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T14CM00889
Permit Description: NEW RETAIL BUILDING
Total Completed Inspections - 48
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/24/2014 | PLUMBING - PRE SLAB | JMILITEL | Approved | OK TO POUR PLUMBING TRENCH & SLAB |
04/24/2014 | PLUMBING - PRE SLAB | JMILITEL | Approved | IVRS - Inspection :* |
04/24/2014 | PLUMBING - ROUGH, SOIL | JMILITEL | Approved | IVRS - Inspection :* |
04/25/2014 | ELECTRIC - UFER | JMILITEL | Approved | IVRS - Inspection :* |
04/29/2014 | BUILDING PRE-SLAB | JMILITEL | Approved | OK TO POUR SLAB |
04/29/2014 | BUILDING PRE-SLAB | JMILITEL | Approved | IVRS - Inspection :* |
05/06/2014 | STEM WALL/RETAINING WALL | JMILITEL | Approved | IVRS - Inspection :* |
05/14/2014 | FIRE SPKLR - UG, PIPING, HYDRO | CSCHULTZ | Approved | placement okay and 200 psi for hours APPROVED Still needs to be flushed |
05/23/2014 | REINFORCED MASONRY PRE-GROUT | JMILITEL | Approved | OK TO TOP-OFF FINAL LIFT PENDING SPECIAL INSPECTION |
05/23/2014 | REINFORCED MASONRY PRE-GROUT | JMILITEL | Approved | IVRS - Inspection :* |
05/28/2014 | FIRE SPKLR - UG PIPING FLUSH | CSCHULTZ | Approved | 2 min 30 sec flush |
06/02/2014 | ROOF NAILING | JBURGE | Approved | OK TO DRY-IN |
06/02/2014 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* |
06/16/2014 | ELECTRIC - UNDERGROUND | JMILITEL | Approved | IVRS - Inspection :* |
06/16/2014 | EXT METAL CLIPS/EXT SHEATHING | JMILITEL | Approved | IVRS - Inspection :* |
06/18/2014 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
06/18/2014 | PLUMBING - ROOF DRAINS | BBENEDON | Approved | IVRS - Inspection :* |
06/19/2014 | ELECTRIC - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
06/24/2014 | ELECTRIC - TEMP POWER FOR TEST | JMILITEL | Approved | IVRS - Inspection :* |
06/24/2014 | ELECTRIC - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
06/24/2014 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
06/24/2014 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
06/24/2014 | BUILDING - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
06/25/2014 | PLUMBING - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
06/25/2014 | SHEET ROCK NAILING | JMILITEL | Approved | IVRS - Inspection :* |
06/25/2014 | FRAMING | JMILITEL | Approved | IVRS - Inspection :* |
07/14/2014 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
07/18/2014 | MECHANICAL - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
07/18/2014 | ELECTRIC - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
07/18/2014 | BUILDING ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
07/18/2014 | STUCCO MESH | BBENEDON | Approved | IVRS - Inspection :* |
07/18/2014 | U VALUE FOR WINDOW | BBENEDON | Approved | IVRS - Inspection :* |
07/23/2014 | FIRE SPKLR - OH PIPING & HYDRO | WMOTTO | Approved | |
08/08/2014 | TEP CLEARANCE - AM | JMILITEL | Approved | ECO |
08/11/2014 | EXCAVATION/LAYOUT REBAR & ZON | JMILITEL | Approved | IVRS - Inspection :* |
08/19/2014 | PLUMBING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
08/22/2014 | ELECTRIC - OUTDOOR LIGHTING | JMILITEL | Approved | IVRS - Inspection :* |
08/22/2014 | ELECTRIC - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
08/25/2014 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
08/25/2014 | BUILDING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
08/25/2014 | RIGHT OF WAY - FINAL | TWOLFGANG | Approved | |
08/25/2014 | NPPO - FINAL | RLEDONNE | Approved | |
08/25/2014 | SIGN - FINAL | RLEDONNE | Approved | |
08/26/2014 | FIRE - FINAL | CSCHULTZ | Approved | |
08/26/2014 | FIRE - ALARM FINAL | CSCHULTZ | Approved | |
08/26/2014 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | |
08/26/2014 | LANDSCAPE - FINAL | MRUSSO | Approved | |
08/26/2014 | ENGINEERING - FINAL | MRUSSO | Approved |