Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 05/23/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
IVRS - Inspection :* |
| 05/23/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
OK TO TOP-OFF FINAL LIFT PENDING SPECIAL INSPECTION |
| 05/22/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 05/22/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT FINAL LIFT EAST & WEST. OK TO GROUT 5TH LIFT NORTH & SOUTH. ALL PENDING SPECIAL INSPECTION |
| 05/20/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 05/20/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT 5TH LIFT PENDING SPECIAL INSPECTION |
| 05/16/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 05/16/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT 4TH LIFT |
| 05/12/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 05/12/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT 3RD LIFT AT EAST, SOUTH, & WEST WALLS |
| 05/07/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 05/07/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT 2ND LIFT PENDING SPECIAL INSPECTION |
| 05/06/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 05/06/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT 1ST LIFT |
| 04/23/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 04/23/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT STEM WALL PENDING SPECIAL INSPECTION |