Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
2550 W SWEETWATER DR
Apply Date:
09/24/2013
Applicant:
JOY TERRY
Description:
NEW AMMONIA BUILDING FOR TREATMENT PLANT
Contractors:
  • C H 2 M HILL CONSTRUCTORS INC ,

Permit Reviews

Permit Number - T13CM05871
Permit Status: C of o
Permit Description: NEW AMMONIA BUILDING FOR TREATMENT PLANT
Start Date Submittal Complete Date Status  
09/24/2013 PLANS OK TO SUBMIT - COMM 09/24/2013 COMPLETED Review Details
09/24/2013 COMMERCIAL - NEW 10/07/2013 COMPLETED Review Details
10/09/2013 RESUBMITTAL 10/09/2013 COMPLETED Review Details
12/06/2013 REVISION - - 1ST 12/06/2013 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T13CM05871
Permit Status: C of o
Permit Description: NEW AMMONIA BUILDING FOR TREATMENT PLANT
Total Outstanding Activity Conditions - 1
Date Name
09/24/2013 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T13CM05871
Permit Description: NEW AMMONIA BUILDING FOR TREATMENT PLANT
Total Completed Inspections - 32
Date Description Inspector Results Comments
11/04/2013 PLUMBING - YARD WTR LINE/TEST RMYERS Approved 1. 30" DIP reclaimed tied into existing OK. OK to cover.
11/08/2013 ELECTRIC - UFER DQUINN Approved
11/08/2013 EXCAVATION/LAYOUT REBAR & ZON DQUINN Approved MAIN AMONIA BUILDING MATS AND UFER OK TO POUR
11/13/2013 STEM WALL/RETAINING WALL MPUGH Approved STEM WALL OK TO POUR
11/13/2013 STEM WALL/RETAINING WALL MPUGH Approved IVRS - Inspection :*
11/18/2013 FIRE SPKLR - UG PIPING FLUSH CSCHULTZ Approved
11/18/2013 FIRE SPKLR - UG, PIPING, HYDRO CSCHULTZ Approved 200 PSI for 2 hours
11/26/2013 BUILDING - PROGRESS RMYERS Approved 1. Bonding grid OK. Electric conduit around building and extended ten plus feet South of building OK to cover.
12/10/2013 PLUMBING - INTERMEDIATE RMYERS Approved 1. Ten feet of 36" DIP installed just outside Chlorine Basin.
12/12/2013 ELECTRIC - UNDERGROUND MPUGH Approved NEW DUCT BANK OK TO COVER
12/12/2013 ELECTRIC - UNDERGROUND MPUGH Approved IVRS - Inspection :*
12/19/2013 REINFORCED MASONRY PRE-GROUT RMYERS Approved
01/22/2014 ROOF NAILING RMYERS Approved
01/28/2014 FIRE SPKLR - OH PIPING & HYDRO CSCHULTZ Approved 2 HOURS AND PLACEMENT - APPROVED- CHANGES WERE MADE TO SPRINKLER HEADS PLANS SHOW 155 DEG INSTALLED ARE 200 DEG. HEADS NO COOLER OR A/C FOR ROOM.
02/20/2014 ELECTRIC - ABOVE CEILING RMYERS Approved
02/20/2014 MECHANICAL - INTERMEDIATE RMYERS Approved
02/20/2014 EXT METAL CLIPS/EXT SHEATHING RMYERS Approved
02/20/2014 BUILDING PRE-SLAB RMYERS Approved
03/07/2014 RIGHT OF WAY - FINAL TW Approved
03/10/2014 ELECTRIC - INTERMEDIATE RMYERS Approved
03/10/2014 ELECTRIC - SERVICE UPGRADE RMYERS Approved
03/10/2014 NPPO - FINAL MRUSSO Approved
03/10/2014 SIGN - FINAL MRUSSO Approved
03/10/2014 LANDSCAPE - FINAL MRUSSO Approved
03/10/2014 ENGINEERING - FINAL MRUSSO Approved
03/17/2014 FIRE SPKLR - FINAL CSCHULTZ Approved 2" drain test 100-90-100
03/17/2014 FIRE - ALARM FINAL CSCHULTZ Approved
03/21/2014 ELECTRIC - FINAL RMYERS Approved
03/21/2014 PLUMBING - FINAL RMYERS Approved
03/21/2014 MECHANICAL - FINAL RMYERS Approved
03/24/2014 FIRE - FINAL CSCHULTZ Approved
04/04/2014 BUILDING - FINAL RMYERS Approved