Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 03/10/2014 |
BUILDING - PROGRESS |
|
Approved |
|
| 02/28/2014 |
BUILDING - PROGRESS |
|
Partial Approval |
1. Pouring sidewalks on North side. |
| 02/03/2014 |
BUILDING - PROGRESS |
|
Partial Approval |
1. Foundation for sump OK for concrete. |
| 01/29/2014 |
BUILDING - PROGRESS |
|
Partial Approval |
1. Epoxy anchors for electric cabinets. |
| 01/17/2014 |
BUILDING - PROGRESS |
|
Partial Approval |
1. Roof decking at Ammonia Bldg. |
| 01/14/2014 |
BUILDING - PROGRESS |
|
Partial Approval |
1. Joist plates for Ammonia Bldg. OK. |
| 01/14/2014 |
BUILDING - PROGRESS |
|
Partial Approval |
1. I Beams set in place at roof. Electric embed anchors at N.E. corner of Ammonia Bldg. |
| 01/13/2014 |
BUILDING - PROGRESS |
|
Partial Approval |
1. Rebar mat in place at Chlorine Containment Basin (CCB) OK for concrete. |
| 01/10/2014 |
BUILDING - PROGRESS |
|
Partial Approval |
1. Chlorine Contact Basin (CCB) at the mixer- checked embeds. Recall before pour. |
| 11/26/2013 |
BUILDING - PROGRESS |
|
Partial Approval |
1. Bonding grid OK. Electric conduit around building and extended ten plus feet South of building OK to cover. |
| 10/16/2013 |
BUILDING - PROGRESS |
|
Partial Approval |
1. Pre-Con with CH2M Hill. Installing 30" DIP reclaimed water with purple tracer attached to extraction well pipe. OK to cover subject to test. |