Permit: T13CM04840
Permit Details
Status:
C of o
Type:
SINGLE FAMILY OTHER
Address:
1570 E TUCSON MARKETPLACE BL #110
Address NEW:
1570 E TUCSON MARKETPLACE BL #110
Apply Date:
08/07/2013
Applicant:
DOUBLE AA BUILDERS LTD
Description:
TI: RETAIL
Contractors:
- DOUBLE A A BUILDERS LTD ,
Permit Reviews
Permit Number - T13CM04840
Permit Status: C of o
Permit Description: TI: RETAIL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/07/2013 | PLANS OK TO SUBMIT - COMM | 08/08/2013 | COMPLETED |
| 08/08/2013 | COMMERCIAL - TI | 09/09/2013 | COMPLETED |
| 09/09/2013 | OTHER | 09/11/2013 | COMPLETED |
| 09/11/2013 | OTHER | 09/13/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM04840
Permit Status: C of o
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/07/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T13CM04840
Permit Description: TI: RETAIL
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/27/2013 | FIRE - FINAL | CBASALDU | Approved | |
| 09/27/2013 | FIRE - ALARM FINAL | CBASALDU | Approved | |
| 09/27/2013 | FIRE SPKLR - FINAL | CBASALDU | Approved | |
| 09/27/2013 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 09/27/2013 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 09/27/2013 | PLUMBING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 09/27/2013 | PLUMBING - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 09/27/2013 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 09/27/2013 | PLUMBING - PRE SLAB | MRAMBER | Approved | IVRS - Inspection :* |
| 09/27/2013 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | IVRS - Inspection :* |
| 09/27/2013 | ELECTRIC - OUTDOOR LIGHTING | MRAMBER | Approved | IVRS - Inspection :* |
| 09/27/2013 | ELECTRIC - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 09/27/2013 | FRAMING | MRAMBER | Approved | IVRS - Inspection :* |
| 09/30/2013 | SHEET ROCK NAILING | MRAMBER | Approved | IVRS - Inspection :* |
| 10/01/2013 | TEP CLEARANCE - AM | MRAMBER | Approved | ECO |
| 10/07/2013 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 10/07/2013 | BUILDING ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 10/11/2013 | ELECTRIC - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 10/11/2013 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 10/11/2013 | PLUMBING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 10/11/2013 | ELECTRIC - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 10/11/2013 | BUILDING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |