Permit: T13CM04783
Permit Details
Apply Date:
08/06/2013
Applicant:
DAVID MAJOR
Description:
TI: OFFICE
Contractors:
- KALAHAR CONSTRUCTION LLC
Permit Reviews
Permit Number - T13CM04783
Permit Status: Final
Permit Description: TI: OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/06/2013 | COMMERCIAL - TI | 09/09/2013 | COMPLETED |
| 09/09/2013 | WALK THRU - COMM | 09/09/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM04783
Permit Status: Final
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/06/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T13CM04783
Permit Description: TI: OFFICE
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/30/2013 | SITE - SEWER | MPUGH | Approved | IVRS - Inspection :* |
| 09/30/2013 | PLUMBING - YARD WTR LINE/TEST | MPUGH | Approved | IVRS - Inspection :* |
| 09/30/2013 | PLUMBING - PRE SLAB | MPUGH | Approved | IVRS - Inspection :* |
| 09/30/2013 | PLUMBING - ROUGH, SOIL | MPUGH | Approved | IVRS - Inspection :* |
| 10/09/2013 | MECHANICAL - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
| 10/09/2013 | MECHANICAL - INTERMEDIATE | MPUGH | Approved | IVRS - Inspection :* |
| 10/09/2013 | PLUMBING - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
| 10/09/2013 | PLUMBING - INTERMEDIATE | MPUGH | Approved | IVRS - Inspection :* |
| 10/09/2013 | ELECTRIC - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
| 10/09/2013 | ELECTRIC - INTERMEDIATE | MPUGH | Approved | IVRS - Inspection :* |
| 10/09/2013 | BUILDING ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
| 10/09/2013 | FRAMING | MPUGH | Approved | IVRS - Inspection :* |
| 10/16/2013 | ELECTRIC - FINAL | MPUGH | Approved | OK FOR TEMP POWER |
| 10/16/2013 | ELECTRIC - FINAL | MPUGH | Approved | IVRS - Inspection :* |
| 10/17/2013 | TEP CLEARANCE - AM | MPUGH | Approved | TEC |
| 10/22/2013 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 01/14/2014 | FIRE - FINAL | wmotto | Approved | |
| 01/14/2014 | MECHANICAL - FINAL | MPUGH | Approved | IVRS - Inspection :* |
| 01/14/2014 | PLUMBING - FINAL | MPUGH | Approved | IVRS - Inspection :* |
| 01/14/2014 | BUILDING - FINAL | MPUGH | Approved | IVRS - Inspection :* |
| 01/15/2014 | NPPO - FINAL | MRUSSO | Approved | |
| 01/15/2014 | SIGN - FINAL | MRUSSO | Approved | |
| 07/22/2014 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 07/22/2014 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 08/14/2017 | PLUMBING - PROGRESS | MPUGH | Approved |