Permit: T13CM04033
Permit Details
Apply Date:
07/02/2013
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
COMMERCIAL KITCHEN
Architects:
- VOGEL, BENJAMIN ARMANDO
Permit Reviews
Permit Number - T13CM04033
Permit Status: C of o
Permit Description: COMMERCIAL KITCHEN
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/02/2013 | COMMERCIAL - TI | 07/08/2013 | COMPLETED |
07/02/2013 | COMMERCIAL - TI | 07/18/2013 | COMPLETED |
07/08/2013 | COMMERCIAL - TI | 07/15/2013 | COMPLETED |
07/18/2013 | COMMERCIAL - TI | 07/22/2013 | COMPLETED |
07/22/2013 | COMMERCIAL - TI | 07/22/2013 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T13CM04033
Permit Description: COMMERCIAL KITCHEN
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/23/2013 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | TEST ALL JOINTS ABOVE SLAB |
07/23/2013 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
07/24/2013 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
08/07/2013 | FRAMING | JBURGE | Approved | OK TO SHEETROCK |
08/07/2013 | PLUMBING - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
08/07/2013 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
08/09/2013 | SHEET ROCK NAILING | JBURGE | Approved | OK TO TAPE THROUGOUT |
08/09/2013 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
08/29/2013 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
08/30/2013 | MECHANICAL - HOODS | JBURGE | Approved | IVRS - Inspection :* |
09/10/2013 | LANDSCAPE - FINAL | DROBERTS | Approved | |
09/10/2013 | SIGN - FINAL | DROBERTS | Approved | |
09/10/2013 | NPPO - FINAL | DROBERTS | Approved | |
09/10/2013 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
09/10/2013 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
09/10/2013 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
09/10/2013 | PLUMBING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
09/10/2013 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | IVRS - Inspection :* |
09/10/2013 | PLUMBING - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
09/10/2013 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
09/16/2013 | ELECTRIC - FINAL | JBURGE | Approved | IVRS - Inspection :* |
10/04/2013 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
10/04/2013 | PLUMBING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
10/04/2013 | MECHANICAL - FINAL | JBURGE | Approved | IVRS - Inspection :* |
10/23/2013 | FIRE - FINAL | STATE/TFD | Approved | STATE INSPECTED ALARMS. TFD INSPECTED HOOD |
10/23/2013 | HEALTH DEPT - FINAL 724-7908 | NRAMIREZ | Approved | |
10/23/2013 | RIGHT OF WAY - FINAL | LHANLY | Approved | THIS IS INTERIOR TI WORK ONLY ON EXISTING BUILDING. ALL SITE AND R.O.W. WORK IS BEING DONE UNDER SEPARATE PERMIT |
10/23/2013 | ENGINEERING - FINAL | LHANLY | Approved | THIS IS INTERIOR TI ONLY. ALL SITE WORK IS BEING DONE UNDER SEPARATE PERMIT |