Permit: T13CM02068
Permit Details
Status:
C of o
Type:
COMMERCIAL ADDITION
Address:
510 S HIGHLAND AV 02
Address NEW:
510 S HIGHLAND AV 02
Apply Date:
04/09/2013
Applicant:
FORD, WILLIAM LESLEY
Description:
DETACHED NEW CLASSROOM BUILDING
Architects:
- FORD, WILLIAM LESLEY
Permit Reviews
Permit Number - T13CM02068
Permit Status: C of o
Permit Description: DETACHED NEW CLASSROOM BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/09/2013 | PLANS OK TO SUBMIT - COMM | 04/09/2013 | COMPLETED |
| 04/10/2013 | COMMERCIAL - NEW | 04/24/2013 | COMPLETED |
| 04/30/2013 | RESUBMITTAL | 05/10/2013 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T13CM02068
Permit Description: DETACHED NEW CLASSROOM BUILDING
Total Completed Inspections - 33
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/20/2013 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | IVRS - Inspection :* |
| 05/20/2013 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | IVRS - Inspection :* |
| 05/21/2013 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* |
| 05/29/2013 | EXT METAL CLIPS/EXT SHEATHING | MRAMBER | Approved | IVRS - Inspection :* |
| 05/29/2013 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | IVRS - Inspection :* |
| 06/04/2013 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 06/04/2013 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 06/04/2013 | U VALUE FOR WINDOW | MRAMBER | Approved | IVRS - Inspection :* |
| 06/04/2013 | FRAMING | MRAMBER | Approved | IVRS - Inspection :* |
| 06/05/2013 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 06/05/2013 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 06/05/2013 | ROOF NAILING | MRAMBER | Approved | IVRS - Inspection :* |
| 06/12/2013 | SHEET ROCK NAILING | MRAMBER | Approved | IVRS - Inspection :* |
| 06/12/2013 | SITE - SEWER | MRAMBER | Approved | IVRS - Inspection :* |
| 06/14/2013 | STUCCO MESH | MRAMBER | Approved | IVRS - Inspection :* |
| 07/23/2013 | PLUMBING - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 07/23/2013 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 07/23/2013 | BUILDING ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 08/09/2013 | RIGHT OF WAY - FINAL | TWOLFGAN | Approved | |
| 08/09/2013 | PLUMBING - PRE SLAB | MRAMBER | Approved | PER PLMB FINAL - MRAMBER |
| 08/09/2013 | BUILDING - PROGRESS | MRAMBER | Approved | PER BLDG FINAL - MRAMBER |
| 08/09/2013 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 08/09/2013 | PLUMBING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 08/09/2013 | ELECTRIC - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 08/09/2013 | BUILDING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 08/12/2013 | PLUMBING - PROGRESS | MRAMBER | Approved | PER PLMB FINAL |
| 08/12/2013 | NPPO - FINAL | RLEDONNE | Approved | |
| 08/12/2013 | SIGN - FINAL | RLEDONNE | Approved | |
| 08/12/2013 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 08/12/2013 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 08/15/2013 | FIRE SPKLR - FINAL | ASFM | Approved | APROVAL FROM ASFM INSPECTOR FRED DURHAM |
| 08/30/2013 | FIRE - FINAL | ASFM | Approved | |
| 08/30/2013 | FIRE - ALARM FINAL | ASFM | Approved |