Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T13CM01837
Permit Details
Apply Date:
04/01/2013
Applicant:
PHIL TOLLIOS
Description:
TI: RETAIL
Architects:
- HEATH, DENNIS MICHAEL
Contractors:
- CONSTRUCTION SOLUTIONS INC OF TEXAS
Permit Reviews
Permit Number - T13CM01837
Permit Status: C of o
Permit Description: TI: RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/01/2013 | PLANS OK TO SUBMIT - COMM | 05/06/2013 | COMPLETED |
05/06/2013 | COMMERCIAL - TI | 05/24/2013 | COMPLETED |
05/24/2013 | RESUBMITTAL | 05/29/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM01837
Permit Status: C of o
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/01/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T13CM01837
Permit Description: TI: RETAIL
Total Completed Inspections - 36
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/18/2013 | PLUMBING - ROUGH, SOIL | DSANTACR | Approved | IVRS - Inspection :* |
07/08/2013 | REINFORCED MASONRY PRE-GROUT | DSANTACR | Approved | IVRS - Inspection :* |
07/12/2013 | PLUMBING - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
07/16/2013 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
07/16/2013 | FRAMING | DSANTACR | Approved | IVRS - Inspection :* |
07/30/2013 | PLUMBING - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
07/30/2013 | STUCCO MESH | DSANTACR | Approved | IVRS - Inspection :* |
08/05/2013 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
08/05/2013 | SHEET ROCK NAILING | RCAMACHO | Approved | IVRS - Inspection :* |
08/07/2013 | PLUMBING - GAS PRESSURE TEST | DSANTACR | Approved | IVRS - Inspection :* |
08/15/2013 | PLUMBING - ROOF DRAINS | DSANTACR | Approved | IVRS - Inspection :* |
08/23/2013 | TEP CLEARANCE - AM | RMORENO | Approved | INCR |
08/30/2013 | MECHANICAL - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |
08/30/2013 | MECHANICAL - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
08/30/2013 | ELECTRIC - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |
08/30/2013 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
08/30/2013 | BUILDING - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |
08/30/2013 | BUILDING ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
09/04/2013 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | IVRS - Inspection :* |
09/06/2013 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
09/06/2013 | U VALUE FOR WINDOW | DSANTACR | Approved | IVRS - Inspection :* |
09/13/2013 | LANDSCAPE - FINAL | DROBERTS | Approved | |
09/13/2013 | SIGN - FINAL | DROBERTS | Approved | |
09/13/2013 | NPPO - FINAL | DROBERTS | Approved | |
09/17/2013 | FIRE - ALARM FINAL | CSCHULTZ | Approved | |
09/18/2013 | PLUMBING - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
09/18/2013 | PLUMBING - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |
09/19/2013 | ELECTRIC - SERVICE RELOCATION | DSANTACR | Approved | |
09/19/2013 | MECHANICAL - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
09/19/2013 | BUILDING - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
09/19/2013 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
09/19/2013 | RIGHT OF WAY - FINAL | JC | Approved | |
09/25/2013 | ENGINEERING - FINAL | DROBERTS | Approved | ALLEY WAY IN THE REVISED DRAWINGS IS NOTED AT 20 FEET WIDE NOT 24 FEET, ALL IS GOOD AT THIS TIME. |
09/25/2013 | ENGINEERING - FINAL | DROBERTS | Approved | ALLEY ACCESS HAS BEEN REDUCED BELOW 24 FOOT AS SHOWN ON THE ORIGINAL PLANS, AND HANDICAP ACCESS HAS NOT BEEN CONSTRUCTED AS SHOWN. SIGNS FOR THE ADA SPACES ARE LESS THAN 7 FEET ABOVE THE FINISH GRADE AND WILL BE ADJUSTED. |
09/25/2013 | FIRE SPKLR - FINAL | CBOSALDUA | Approved | |
09/25/2013 | FIRE - FINAL | CBOSALDUA | Approved |