Permit: T13CM01787
Permit Details
Apply Date:
03/28/2013
Applicant:
CAROLINE SHAW C/O GREENBERGFARROW
Description:
NEW RETAIL BUILDING
Contractors:
- M C O AND ASSOCIATES L L C
Permit Reviews
Permit Number - T13CM01787
Permit Status: C of o
Permit Description: NEW RETAIL BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/28/2013 | PLANS OK TO SUBMIT - COMM | 03/28/2013 | COMPLETED |
| 03/28/2013 | COMMERCIAL - NEW | 04/18/2013 | COMPLETED |
| 04/15/2014 | REVISION - - 1ST | 04/15/2014 | COMPLETED |
| 05/09/2013 | RESUBMITTAL | 09/26/2013 | COMPLETED |
| 09/26/2013 | RESUBMITTAL | 10/14/2013 | COMPLETED |
| 10/14/2013 | RESUBMITTAL | 10/15/2013 | COMPLETED |
| 10/15/2013 | RESUBMITTAL | 04/15/2014 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM01787
Permit Status: C of o
Permit Description: NEW RETAIL BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/28/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T13CM01787
Permit Description: NEW RETAIL BUILDING
Total Completed Inspections - 43
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/23/2014 | PLUMBING - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 07/30/2014 | SHEET ROCK NAILING | MRAMBER | Approved | IVRS - Inspection :* |
| 07/30/2014 | STUCCO MESH | MRAMBER | Approved | IVRS - Inspection :* |
| 08/18/2014 | PLUMBING - YARD WTR LINE/TEST | RCAMACHO | Approved | IVRS - Inspection :* |
| 08/21/2014 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | |
| 08/21/2014 | SITE - SEWER | RLEDONNE | Approved | |
| 08/27/2014 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | IVRS - Inspection :* |
| 08/29/2014 | ELECTRIC - UNDERGROUND | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/03/2014 | PLUMBING - PRE SLAB | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/03/2014 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/03/2014 | FRAMING | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/03/2014 | ROOF NAILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/03/2014 | EXT METAL CLIPS/EXT SHEATHING | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/03/2014 | BUILDING PRE-SLAB | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/04/2014 | REINFORCED MASONRY PRE-GROUT | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/12/2014 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | IVRS - Inspection :* |
| 09/15/2014 | TEP CLEARANCE - AM | DSANTACRUZ | Approved | TEC |
| 09/25/2014 | MECHANICAL - ABOVE CEILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/25/2014 | PLUMBING - ABOVE CEILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/25/2014 | ELECTRIC - ABOVE CEILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/25/2014 | BUILDING ABOVE CEILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/26/2014 | ELECTRIC - OUTDOOR LIGHTING | RCAMACHO | Approved | |
| 09/26/2014 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/26/2014 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/26/2014 | ELECTRIC - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/30/2014 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 09/30/2014 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 09/30/2014 | U VALUE FOR WINDOW | MRAMBER | Approved | IVRS - Inspection :* |
| 10/01/2014 | HEALTH DEPT - FINAL 724-7908 | RLOPEZ | Approved | |
| 10/02/2014 | BUILDING - PROGRESS | MRAMBER | Approved | |
| 10/02/2014 | ELECTRIC - UFER | MRAMBER | Approved | |
| 10/02/2014 | ELECTRIC - PROGRESS | MRAMBER | Approved | |
| 10/02/2014 | PLUMBING - PROGRESS | MRAMBER | Approved | |
| 10/02/2014 | STEM WALL/RETAINING WALL | MRAMBER | Approved | |
| 10/02/2014 | PLUMBING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 10/02/2014 | BUILDING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 10/02/2014 | RIGHT OF WAY - FINAL | RHNAT | Approved | |
| 10/02/2014 | FIRE - FINAL | JVINCENT | Approved | |
| 10/02/2014 | NPPO - FINAL | RLEDONNE | Approved | |
| 10/02/2014 | SIGN - FINAL | RLEDONNE | Approved | |
| 10/07/2014 | FIREWALL/FIREBARRIER/FIRESTOP | RLEDONNE | Approved | |
| 10/07/2014 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 10/07/2014 | ENGINEERING - FINAL | RLEDONNE | Approved |