Permit: T13CM00411
Permit Details
Apply Date:
01/23/2013
Applicant:
DARRELL EPPS
Description:
INSTALL NEW GENERATOR
Contractors:
- D P AIR ,
Permit Reviews
Permit Number - T13CM00411
Permit Status: Final
Permit Description: INSTALL NEW GENERATOR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/23/2013 | PLANS OK TO SUBMIT - COMM | 01/23/2013 | COMPLETED |
| 01/23/2013 | WALK THRU - COMM | 01/23/2013 | COMPLETED |
| 01/23/2013 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 02/20/2013 | COMPLETED |
| 02/28/2013 | RESUBMITTAL | 02/28/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM00411
Permit Status: Final
Permit Description: INSTALL NEW GENERATOR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/23/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T13CM00411
Permit Description: INSTALL NEW GENERATOR
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/05/2013 | ELECTRIC - UNDERGROUND | RMYERS | Approved | IVRS - Inspection :* ELECTRIC UNDER SLAB OK GROUNDING OK EXCAVATION LAYOUT AND REBAR OK OK FOR CONCRETE |
| 06/24/2013 | ELECTRIC - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
| 06/25/2013 | NPPO - FINAL | RLEDONNE | Approved | |
| 06/25/2013 | SIGN - FINAL | RLEDONNE | Approved | |
| 06/25/2013 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 06/25/2013 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 06/26/2013 | FIRE - FINAL | CBASALDU | Approved | |
| 06/26/2013 | ELECTRIC - INTERMEDIATE | RMYERS | Approved | PER ELEC FINAL |
| 06/26/2013 | ELECTRIC - FINAL | MPUGH | Approved | IVRS - Inspection :* |
| 06/27/2013 | RIGHT OF WAY - FINAL | TWOLFGAN | Approved |