Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T12CM08260
Permit Details
Apply Date:
12/31/2012
Applicant:
N/A
Description:
TAVERN
Architects:
- FUENTEVILLA, MIGUEL RAUL
Contractors:
- HOPE CONSTRUCTION L L C
Permit Reviews
Permit Number - T12CM08260
Permit Status: C of o
Permit Description: TAVERN
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/07/2013 | COMMERCIAL - TI | 02/15/2013 | COMPLETED |
02/28/2013 | RESUBMITTAL | 03/27/2013 | COMPLETED |
03/27/2013 | RESUBMITTAL | 04/02/2013 | ACTIVE |
12/31/2012 | PLANS OK TO SUBMIT - COMM | 01/03/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM08260
Permit Status: C of o
Permit Description: TAVERN
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/31/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM08260
Permit Description: TAVERN
Total Completed Inspections - 30
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/18/2013 | ELECTRIC - UNDERGROUND | LHANLY | Approved | |
04/18/2013 | ELECTRIC - UFER | LHANLY | Approved | |
04/18/2013 | SHEET ROCK NAILING | LHANLY | Approved | |
04/18/2013 | U VALUE FOR WINDOW | LHANLY | Approved | |
04/18/2013 | BUILDING ABOVE CEILING | LHANLY | Approved | |
04/18/2013 | FRAMING | LHANLY | Approved | |
04/18/2013 | ROOF NAILING | LHANLY | Approved | |
04/18/2013 | BUILDING PRE-SLAB | LHANLY | Approved | |
04/18/2013 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | |
04/18/2013 | PLUMBING - PROGRESS | LHANLY | Approved | |
04/18/2013 | PLUMBING - ABOVE CEILING | LHANLY | Approved | |
04/18/2013 | PLUMBING - INTERMEDIATE | LHANLY | Approved | |
04/18/2013 | PLUMBING - PRE SLAB | LHANLY | Approved | |
04/18/2013 | PLUMBING - ROUGH, SOIL | LHANLY | Approved | |
04/18/2013 | ELECTRIC - ABOVE CEILING | LHANLY | Approved | |
04/18/2013 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | |
04/18/2013 | NPPO - FINAL | LHANLY | Approved | |
04/18/2013 | LANDSCAPE - FINAL | LHANLY | Approved | |
04/18/2013 | ENGINEERING - FINAL | LHANLY | Approved | |
05/09/2013 | ELECTRIC - OUTDOOR LIGHTING | LHANLY | Approved | |
05/09/2013 | ELECTRIC - PROGRESS | LHANLY | Approved | |
05/09/2013 | BUILDING - PROGRESS | LHANLY | Approved | |
05/09/2013 | MECHANICAL - INTERMEDIATE | LHANLY | Approved | |
08/29/2013 | TEP CLEARANCE - AM | LHANLY | Approved | ECO |
09/06/2013 | FIRE - FINAL | wmotto | Approved | |
09/06/2013 | BUILDING - FINAL | LHANLY | Approved | |
09/06/2013 | MECHANICAL - FINAL | LHANLY | Approved | |
09/06/2013 | MECHANICAL - ABOVE CEILING | LHANLY | Approved | |
09/06/2013 | PLUMBING - FINAL | LHANLY | Approved | |
09/06/2013 | ELECTRIC - FINAL | LHANLY | Approved |