Permit: T12CM07703
Permit Details
Apply Date:
12/05/2012
Applicant:
JACA DESIGN LLC
Description:
TI: RETAIL
Contractors:
- BARCELO BUILDERS LLC
Permit Reviews
Permit Number - T12CM07703
Permit Status: Expired
Permit Description: TI: RETAIL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/25/2013 | REVISION - - 1ST | 02/25/2013 | COMPLETED |
| 12/05/2012 | COMMERCIAL - TI | 01/04/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM07703
Permit Status: Expired
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/05/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Expired
Permit Number: T12CM07703
Permit Description: TI: RETAIL
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/15/2013 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | IVRS - Inspection :* |
| 01/15/2013 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 01/15/2013 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 01/28/2013 | SITE - SEWER | BBENEDON | Approved | IVRS - Inspection :* |
| 01/28/2013 | ELECTRIC - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 01/29/2013 | NPPO - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
| 01/29/2013 | SIGN - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
| 01/29/2013 | LANDSCAPE - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
| 01/31/2013 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 01/31/2013 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
| 02/01/2013 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :*OK TO COVER |
| 02/01/2013 | SHEET ROCK NAILING | BBENEDON | Approved | IVRS - Inspection :* |
| 02/19/2013 | PLUMBING - PROGRESS | RMORENO | Approved | 1. low voltage to be removed to jbox 2. pipe and flex to be strapped 3. cooler termination to be inspection ground missing 4. llight fixtures to be installed completely 5. ceiling boxes missing k.o seals 6. strap mc at backroom 7. gfi missing in retail 8. roof to be inspected 9. compressor fuss paperwork missing labes |
| 02/19/2013 | PLUMBING - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 02/26/2013 | MECHANICAL - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 02/27/2013 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 02/27/2013 | MECHANICAL - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 03/07/2013 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
| 03/07/2013 | FIRE - FINAL | CBASALDU | Approved | |
| 03/07/2013 | BUILDING - FINAL | BBENEDON | Approved | IVRS - Inspection :* HB VAC BREAKERS REQ. ON ALL HOSE CONNECTIONS |
| 03/07/2013 | BUILDING ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 03/07/2013 | ENGINEERING - FINAL | DROBERTS | Approved |