Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/19/2013 | PLUMBING - PROGRESS | Approved | 1. low voltage to be removed to jbox 2. pipe and flex to be strapped 3. cooler termination to be inspection ground missing 4. llight fixtures to be installed completely 5. ceiling boxes missing k.o seals 6. strap mc at backroom 7. gfi missing in retail 8. roof to be inspected 9. compressor fuss paperwork missing labes |
|
| 02/14/2013 | PLUMBING - PROGRESS | Not ready for Inspection | complee work and noted corrections protect line set insulation protect exposed plastic will not alien horizontial abs abv roof. provide a plan revision for new a/c units include required fresh air makeup seal all threaded openings in dwv system suppport exp tank and piping.Pipe relief valve to exterior install hose thread vacuum breaker strerliation as specified with documentation | |
| 02/01/2013 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 01/28/2013 | PLUMBING - PROGRESS | Partial Approval | INTERCEPTOR OK CAST IRON OR GALVANIZED REQUIRED ON EXPOSED EXTERIOR |