Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
6310 E BROADWAY BL
Apply Date:
11/21/2012
Applicant:
KATHLEN WALP
Description:
RETAIL / PHARMACY
Contractors:
  • GILBANE BUILDING COMPANY ,

Permit Reviews

Permit Number - T12CM07440
Permit Status: C of o
Permit Description: RETAIL / PHARMACY
Start Date Submittal Complete Date Status  
01/09/2013 COMMERCIAL - NEW 02/13/2013 COMPLETED Review Details
03/06/2013 RESUBMITTAL 03/11/2013 COMPLETED Review Details
03/11/2013 RESUBMITTAL 03/13/2013 ACTIVE Review Details
11/21/2012 PLANS OK TO SUBMIT - COMM 11/21/2012 COMPLETED Review Details
11/21/2012 COMMERCIAL - NEW 12/19/2012 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T12CM07440
Permit Status: C of o
Permit Description: RETAIL / PHARMACY
Total Outstanding Activity Conditions - 1
Date Name
11/21/2012 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T12CM07440
Permit Description: RETAIL / PHARMACY
Total Completed Inspections - 52
Date Description Inspector Results Comments
06/05/2013 ELECTRIC - UFER JBURGE Approved IVRS - Inspection :*
06/10/2013 FIRE SPKLR - UG, PIPING, HYDRO CSCHULTZ Approved 200 PSI for 2 hours approved and placement all piping wraped and wire placed
06/14/2013 PLUMBING - SEWER HCS CONNECT BBENEDON Approved IVRS - Inspection :*
06/17/2013 PLUMBING - ROUGH, SOIL JBURGE Approved PREVIOUS "Y" CORRECTIONS COMPLETED; COPPER LINE SET AT 150 PSI - OK TO COVER
06/17/2013 PLUMBING - ROUGH, SOIL JBURGE Approved IVRS - Inspection :*
06/19/2013 STEM WALL/RETAINING WALL JBURGE Approved CONTINUOUS STEM WALLS
06/19/2013 STEM WALL/RETAINING WALL JBURGE Approved IVRS - Inspection :*
06/25/2013 PLUMBING - PRE SLAB JBURGE Approved IVRS - Inspection :*
06/25/2013 BUILDING PRE-SLAB JBURGE Approved IVRS - Inspection :*
08/08/2013 REINFORCED MASONRY PRE-GROUT JBURGE Approved TRASH ENCLOSURE & COMPACTOR COMPLETE
08/08/2013 REINFORCED MASONRY PRE-GROUT JBURGE Approved IVRS - Inspection :*
08/23/2013 FIRE SPKLR - UG PIPING FLUSH CBASALDU Approved
08/23/2013 ELECTRIC - INTERMEDIATE JBURGE Approved IVRS - Inspection :*
08/28/2013 PLUMBING - ROOF DRAINS JBURGE Approved IVRS - Inspection :*
09/03/2013 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
09/05/2013 PLUMBING - INTERMEDIATE JBURGE Approved OK TO SHEETROCK PLUMBING AREAS
09/05/2013 PLUMBING - INTERMEDIATE JBURGE Approved IVRS - Inspection :*
09/11/2013 FIRE SPKLR - OH PIPING & HYDRO CSCHULTZ Approved 200 PSI for 2 hours and placement APPROVED
09/12/2013 FRAMING JBURGE Approved IVRS - Inspection :*
09/18/2013 MECHANICAL - ABOVE CEILING JBURGE Approved IVRS - Inspection :*
09/18/2013 PLUMBING - ABOVE CEILING JBURGE Approved IVRS - Inspection :*
09/18/2013 ELECTRIC - CABLE DROP JBURGE Approved IVRS - Inspection :*
09/18/2013 ELECTRIC - ABOVE CEILING JBURGE Approved IVRS - Inspection :*
09/18/2013 BUILDING ABOVE CEILING JBURGE Approved IVRS - Inspection :*
09/19/2013 TEP CLEARANCE - AM JBURGE Approved ECO
09/30/2013 ELECTRIC - OUTDOOR LIGHTING JBURGE Approved IVRS - Inspection :*
09/30/2013 ELECTRIC - PROGRESS JBURGE Approved IVRS - Inspection :*
09/30/2013 OUTDOOR LIGHTING FINAL JBURGE Approved IVRS - Inspection :*
09/30/2013 ELECTRIC - FINAL JBURGE Approved IVRS - Inspection :*
10/02/2013 MECHANICAL - INTERMEDIATE JBURGE Approved IVRS - Inspection :*
10/02/2013 PLUMBING - GAS PRESSURE TEST JBURGE Approved IVRS - Inspection :*
10/02/2013 PLUMBING - YARD WTR LINE/TEST JBURGE Approved IVRS - Inspection :*
10/02/2013 ELECTRIC - TEMPORARY SERVICE JBURGE Approved IVRS - Inspection :*
10/02/2013 ELECTRIC - UNDERGROUND JBURGE Approved IVRS - Inspection :*
10/02/2013 U VALUE FOR WINDOW JBURGE Approved IVRS - Inspection :*
10/02/2013 STUCCO MESH JBURGE Approved IVRS - Inspection :*
10/02/2013 ROOF NAILING JBURGE Approved IVRS - Inspection :*
10/02/2013 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved IVRS - Inspection :*
10/02/2013 BUILDING - PROGRESS JBURGE Approved IVRS - Inspection :*
10/03/2013 FIRE - ALARM FINAL CBASALDU Approved
10/03/2013 NPPO - FINAL MRUSSO Approved
10/03/2013 SIGN - FINAL MRUSSO Approved
10/03/2013 LANDSCAPE - FINAL MRUSSO Approved ALL REMAINING STABILIZATION REQUIREMENTS SHOWN ON THE APPROVED PLANS WILL BE ADDRESSED UNDER PERMIT#DP12-0183
10/03/2013 ENGINEERING - FINAL MRUSSO Approved ALL REMAINING STABILIZATION REQUIREMENTS SHOWN ON THE APPROVED PLANS WILL BE ADDRESSED UNDER PERMIT#DP12-0183
10/04/2013 FIRE - FINAL CBASALDU Approved
10/04/2013 FIRE SPKLR - FINAL CBASALDU Approved
10/04/2013 RIGHT OF WAY - FINAL DROBERTS Approved OK PER PHONE CALL
10/04/2013 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved
10/04/2013 PLUMBING - PROGRESS JBURGE Approved
10/04/2013 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*
10/04/2013 MECHANICAL - FINAL JBURGE Approved IVRS - Inspection :*
10/04/2013 PLUMBING - FINAL JBURGE Approved IVRS - Inspection :*