Permit: T12CM05578
Permit Details
Apply Date:
09/06/2012
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: FACADE REMODEL
Contractors:
- BARKER MORRISSEY CONTRACTING INC **APA**
Permit Reviews
Permit Number - T12CM05578
Permit Status: Final
Permit Description: TI: FACADE REMODEL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/06/2012 | PLANS OK TO SUBMIT - COMM | 09/06/2012 | COMPLETED |
09/06/2012 | COMMERCIAL - TI | 09/19/2012 | COMPLETED |
09/19/2012 | RESUBMITTAL | 09/28/2012 | COMPLETED |
09/28/2012 | RESUBMITTAL | 09/28/2012 | ACTIVE |
Completed Inspections
Permit Status: Final
Permit Number: T12CM05578
Permit Description: TI: FACADE REMODEL
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/09/2012 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* |
11/09/2012 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* |
11/09/2012 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* |
11/20/2012 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
11/20/2012 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* |
11/26/2012 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
11/29/2012 | NPPO - FINAL | MRUSSO | Approved | |
11/29/2012 | SIGN - FINAL | MRUSSO | Approved | |
11/29/2012 | LANDSCAPE - FINAL | MRUSSO | Approved | |
11/29/2012 | RIGHT OF WAY - FINAL | P.Whiddon | Approved | |
12/03/2012 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* |
12/03/2012 | ENGINEERING - FINAL | MRUSSO | Approved | |
12/04/2012 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
12/04/2012 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* |
12/04/2012 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
12/05/2012 | FIRE - FINAL | CSCHULTZ | Approved | |
12/05/2012 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | |
12/05/2012 | FIRE - FINAL | CSCHULTZ | Approved | Replace taped and painted heads in the following areas: TV section, Recliners, dinning room tables. X10 Remove two heads next to duct work need to be 4" inches or more away by TV's and Recliners area. In janitors closet install a ceiling or extend walls all the away to the deck or install uprights above ceiling throughout office and restrooms. Need new cal plate. Need a clear access to the inspectors' valve on the southwest corner wall. Need to test the flow switch with the inspectors test valve that is buried behind the wall southwest corner. Need lock out on breaker for alarm panel. |
12/05/2012 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | Replace taped and painted heads in the following areas: TV section, Recliners, dinning room tables. X10 Remove two heads next to duct work need to be 4" inches or more away by TV's and Recliners area. In janitors closet install a ceiling or extend walls all the away to the deck or install uprights above ceiling throughout office and restrooms. Need new cal plate. Need a clear access to the inspectors' valve on the southwest corner wall. Need to test the flow switch with the inspectors test valve that is buried behind the wall southwest corner. Need lock out on breaker for alarm panel. |
12/05/2012 | SHEET ROCK NAILING | JBURGE | Approved | OK PER BUILDING FINAL |
12/05/2012 | BUILDING ABOVE CEILING | JBURGE | Approved | OK PER BUILDING FINAL |