Permit: T12CM05125
Permit Details
Apply Date:
08/20/2012
Applicant:
GARETT CUNNINGHAM
Description:
TI:THEATER
Architects:
- CDG ARCHITECTS
Contractors:
- G AND J DEVELOPMENT INC ,
Permit Reviews
Permit Number - T12CM05125
Permit Status: C of o
Permit Description: TI:THEATER
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/20/2012 | COMMERCIAL - TI | 08/28/2012 | COMPLETED |
08/28/2012 | COMMERCIAL - TI | 09/12/2012 | COMPLETED |
10/09/2012 | REVISION - - 1ST | 10/10/2012 | COMPLETED |
11/01/2012 | REVISION - - 2ND | 11/02/2012 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T12CM05125
Permit Status: C of o
Permit Description: TI:THEATER
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/20/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM05125
Permit Description: TI:THEATER
Total Completed Inspections - 30
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/26/2012 | PLUMBING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
09/26/2012 | PLUMBING - ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
09/26/2012 | PLUMBING - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
09/26/2012 | PLUMBING - ROUGH, SOIL | AQUIROZ | Approved | IVRS - Inspection :* |
10/04/2012 | FRAMING | RHOLLAND | Approved | IVRS - Inspection :* |
10/05/2012 | PLUMBING - PRE SLAB | RHOLLAND | Approved | IVRS - Inspection :* |
10/05/2012 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
10/16/2012 | BUILDING ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
10/30/2012 | ELECTRIC - UNDERGROUND | RMYERS | Approved | IVRS - Inspection :* |
10/31/2012 | RIGHT OF WAY - FINAL | TWOLFGAN | Approved | |
11/01/2012 | NPPO - FINAL | RLEDONNE | Approved | |
11/01/2012 | SIGN - FINAL | RLEDONNE | Approved | |
11/01/2012 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
11/06/2012 | ELECTRIC - SERVICE UPGRADE | AQUIROZ | Approved | IVRS - Inspection :* |
11/07/2012 | SHEET ROCK NAILING | LHANLY | Approved | |
11/07/2012 | TEP CLEARANCE - AM | AQUIROZ | Approved | CLEAR ELEC. (INCR) |
11/08/2012 | FIRE - FINAL | P.December | Approved | all previous inspector issues fixed. Third exit issue was cleared up with Ken B on fire side, and by looking at approved plans on site.. Only two exits required and show on approved plan drawings. Demo sheet shows new doorway for outside entry restroom, as well as approved plans showing those as the only three doors to outside of building. |
11/29/2012 | ZONING - FINAL | DROBERTS | Approved | |
11/29/2012 | ZONING - FINAL | DROBERTS | Approved | MET IN THE OFFICE WITH MANAGEMENT PERSONNEL TO DISCUSS MY ISSUES WITH THIS SITE FOR A FINAL APPROVAL. IT HAS BEEN DECIDED THAT THE SITE CAN BE APPROVED WITH THE FOLLOWING CONDITION: 1) ALLOWING THE REQUIRED PARKING TO BE PROVIDED IN A PARKING LOT AVAILABLE ON THE ADJACENT SITE TOO THE WEST. 2) THE ENCLOSURE OF THE MECHANICAL EQUIPMENT WOULD NOT CONSTATUTE A VIOLATION OF THE COMPLIANCE ORDINANCE. |
11/29/2012 | ENGINEERING - FINAL | DROBERTS | Approved | |
12/18/2012 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
12/18/2012 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | |
12/18/2012 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | |
12/18/2012 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | PROGRESS AREAS |
12/18/2012 | PLUMBING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
12/18/2012 | ELECTRIC - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
12/18/2012 | ELECTRIC - INTERMEDIATE | JMILITEL | Approved | |
12/18/2012 | ELECTRIC - UFER | JMILITEL | Approved | |
12/18/2012 | BUILDING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
12/18/2012 | BUILDING PRE-SLAB | JMILITEL | Approved |