Permit: T12CM04337
Permit Details
Apply Date:
07/18/2012
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
APARTMENT
Architects:
- ACORN, KIM BRIAN
Contractors:
- MCCW BUILDERS LLC
Permit Reviews
Permit Number - T12CM04337
Permit Status: C of o
Permit Description: APARTMENT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/05/2015 | REVISION - - 1ST | 05/05/2015 | COMPLETED |
05/05/2015 | REVISION - - 1ST | 08/18/2015 | COMPLETED |
07/18/2012 | PLANS OK TO SUBMIT - COMM | 07/18/2012 | COMPLETED |
07/23/2012 | COMMERCIAL - NEW | 08/30/2012 | COMPLETED |
08/30/2012 | RESUBMITTAL | 10/04/2012 | COMPLETED |
10/04/2012 | RESUBMITTAL | 11/06/2012 | COMPLETED |
10/14/2014 | RESUBMITTAL | 11/05/2014 | COMPLETED |
11/05/2014 | RESUBMITTAL | 05/05/2015 | COMPLETED |
11/06/2012 | RESUBMITTAL | 10/14/2014 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM04337
Permit Status: C of o
Permit Description: APARTMENT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/18/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM04337
Permit Description: APARTMENT
Total Completed Inspections - 43
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/07/2015 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | |
06/04/2015 | BUILDING PRE-SLAB | JBURGE | Approved | OK TO POUR SLABS |
06/04/2015 | PLUMBING - PRE SLAB | JBURGE | Approved | IVRS - Inspection :* |
06/04/2015 | ELECTRIC - UFER | JBURGE | Approved | IVRS - Inspection :* |
06/04/2015 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* |
06/24/2015 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | 1 ALARM PVC 4 TO 5 BUILDING IN TRENCH OK 2 SITE LIGHTING PVC IN TRENCH OK 3 TEMP POWER FOR 4 AND 5 TRENCH # 1/0 OK 4 SITE LITING 4 AND 5 OK IN TRENCH. |
06/24/2015 | ELECTRIC - TEMPORARY SERVICE | RMORENO | Approved | IVRS - Inspection :* |
07/31/2015 | PLUMBING - SEWER HCS CONNECT | JBURGE | Approved | IVRS - Inspection :* |
08/10/2015 | FIRE - HYDRANTS | CSCHULTZ | Approved | Hydrants in place and in service |
09/08/2015 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :*partial deck nailing for 2nd floor |
09/11/2015 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* |
10/12/2015 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* |
10/30/2015 | PLUMBING - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
11/09/2015 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
11/09/2015 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
11/09/2015 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
11/20/2015 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
12/06/2015 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
02/02/2016 | ELECTRIC - FINAL | JBURGE | Approved | IVRS - Inspection :* |
02/19/2016 | FIRE - ALARM FINAL | cclark1 | Approved | |
02/19/2016 | FIRE - LANE SIGNS | cclark1 | Approved | |
02/19/2016 | FIRE SPKLR - FINAL | cclark1 | Approved | |
02/26/2016 | FIRE - FINAL | CCLARK | Approved | |
03/21/2016 | MECHANICAL - FINAL | JBURGE | Approved | IVRS - Inspection :* |
03/21/2016 | PLUMBING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
03/21/2016 | PLUMBING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
03/21/2016 | PLUMBING - YARD WTR LINE/TEST | JBURGE | Approved | IVRS - Inspection :* |
03/21/2016 | PLUMBING - ROOF DRAINS | JBURGE | Approved | IVRS - Inspection :* |
03/21/2016 | PLUMBING - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
03/21/2016 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | IVRS - Inspection :* |
03/21/2016 | ELECTRIC - CABLE DROP | JBURGE | Approved | IVRS - Inspection :* |
03/21/2016 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
03/21/2016 | ELECTRIC - UNDERGROUND | JBURGE | Approved | IVRS - Inspection :* |
03/21/2016 | FIREWALL/FIREBARRIER/FIRESTOP | JBURGE | Approved | IVRS - Inspection :* |
03/21/2016 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
03/21/2016 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
03/21/2016 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* |
03/21/2016 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
03/23/2016 | RIGHT OF WAY - FINAL | DRUSSELL | Approved | |
03/25/2016 | SIGN - FINAL | DROBERTs | Approved | |
03/25/2016 | LANDSCAPE - FINAL | DROBERTs | Approved | |
03/25/2016 | ENGINEERING - FINAL | DROBERTs | Approved | |
03/25/2016 | NPPO - FINAL | DROBERTs | Approved |