Permit: T12CM04045
Permit Details
Apply Date:
07/06/2012
Applicant:
N/A
Description:
TI: MEDICAL OFFICE, ARIZONA COMMUNITY PHYSICIANS
Architects:
- REYES, RAUL
Contractors:
- TOWN WEST DESIGN DEVELOPMENT INC
Permit Reviews
Permit Number - T12CM04045
Permit Status: C of o
Permit Description: TI: MEDICAL OFFICE, ARIZONA COMMUNITY PHYSICIANS
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/06/2013 | REVISION - - 2ND | 03/12/2013 | COMPLETED |
07/06/2012 | PLANS OK TO SUBMIT - COMM | 07/11/2012 | COMPLETED |
07/12/2012 | COMMERCIAL - TI | 08/13/2012 | COMPLETED |
09/11/2012 | RESUBMITTAL - TI ALL | 10/16/2012 | COMPLETED |
12/12/2012 | REVISION - - 1ST | 12/12/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM04045
Permit Status: C of o
Permit Description: TI: MEDICAL OFFICE, ARIZONA COMMUNITY PHYSICIANS
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/06/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM04045
Permit Description: TI: MEDICAL OFFICE, ARIZONA COMMUNITY PHYSICIANS
Total Completed Inspections - 44
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/22/2012 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | IVRS - Inspection :* |
11/08/2012 | ELECTRIC - UFER | RHOLLAND | Approved | OK 3/0 TO 2 GROUND ROD, 3/0 ADN #6 BONDS OK PVC CONDUITS UNDER SES'S |
11/15/2012 | REINFORCED MASONRY PRE-GROUT | RHOLLAND | Approved | ok top lift equipment yard wall |
12/05/2012 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | IVRS - Inspection :* |
12/05/2012 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | IVRS - Inspection :* |
12/06/2012 | PLUMBING - PRE SLAB | DQUINN | Approved | IVRS - Inspection :* |
12/06/2012 | ELECTRIC - UNDERGROUND | DQUINN | Approved | IVRS - Inspection :* |
12/06/2012 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
12/20/2012 | ELECTRIC - TEMPORARY SERVICE | JMILITEL | Approved | IVRS - Inspection :* |
12/20/2012 | ROOF NAILING | JMILITEL | Approved | IVRS - Inspection :* |
12/20/2012 | EXT METAL CLIPS/EXT SHEATHING | JMILITEL | Approved | IVRS - Inspection :* |
12/20/2012 | TEP CLEARANCE - PM | RHOLLAND | Approved | OK TO CLEAR TEC |
12/21/2012 | ENGINEERING - FINAL | RLEDONNE | Approved | Gave contrator # for right a way inspector. |
12/27/2012 | PLUMBING - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* ROOF DRAINS OK TO COVER. |
01/18/2013 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
01/29/2013 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
02/28/2013 | PLUMBING - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
02/28/2013 | FRAMING | JMILITEL | Approved | IVRS - Inspection :* |
03/05/2013 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
03/05/2013 | ELECTRIC - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
03/20/2013 | FIRE SPKLR - FINAL | CBASALDU | Approved | |
03/20/2013 | ELECTRIC - CONSTRUCTION POWER | RMYERS | Approved | |
03/20/2013 | PLUMBING - PROGRESS | MPUGH | Approved | IVRS - Inspection :* |
03/20/2013 | PLUMBING - YARD WTR LINE/TEST | MPUGH | Approved | IVRS - Inspection :* |
03/20/2013 | ELECTRIC - PROGRESS | MPUGH | Approved | IVRS - Inspection :* |
03/20/2013 | ELECTRIC - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
03/20/2013 | BUILDING - PROGRESS | MPUGH | Approved | IVRS - Inspection :* |
03/20/2013 | STUCCO MESH | MPUGH | Approved | IVRS - Inspection :* |
03/20/2013 | BUILDING ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
03/20/2013 | RIGHT OF WAY - FINAL | P.Whiddon | Approved | |
03/21/2013 | FIRE - FINAL | CSCHULTZ | Approved | |
03/21/2013 | NPPO - FINAL | RLEDONNE | Approved | |
03/21/2013 | SIGN - FINAL | RLEDONNE | Approved | |
03/22/2013 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
03/22/2013 | MECHANICAL - HYDRONIC PIPING | JBURGE | Approved | |
03/22/2013 | MECHANICAL - FINAL | JBURGE | Approved | |
03/22/2013 | PLUMBING - FINAL | JBURGE | Approved | |
03/22/2013 | BUILDING - FINAL | JBURGE | Approved | |
03/22/2013 | ELECTRIC - SERVICE RELOCATION | RMYERS | Approved | |
03/22/2013 | ELECTRIC - FINAL | RMYERS | Approved | |
03/22/2013 | ELECTRIC - TEMP POWER FOR TEST | RMYERS | Approved | |
03/22/2013 | PLUMBING - FINAL | RMYERS | Approved | |
03/22/2013 | MECHANICAL - FINAL | RMYERS | Approved | |
03/22/2013 | BUILDING - FINAL | RMYERS | Approved |