Apply Date:
06/20/2012
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW: TWO STORY CLUBHOUSE
Contractors:
- COLLEGIATE CONSTRUCTION LLC *APA*
Permit Reviews
Permit Number - T12CM03657
Permit Status: C of o
Permit Description: NEW: TWO STORY CLUBHOUSE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/27/2013 | REVISION - - 3RD | 02/28/2013 | COMPLETED |
04/03/2013 | REVISION - - 4TH | 04/05/2013 | COMPLETED |
04/05/2013 | REVISION - - 4TH | 05/09/2013 | COMPLETED |
05/09/2013 | REVISION - - 4TH | 05/17/2013 | COMPLETED |
05/17/2013 | REVISION - - 4TH | 06/06/2013 | COMPLETED |
06/20/2012 | PLANS OK TO SUBMIT - COMM | 06/21/2012 | COMPLETED |
06/27/2012 | COMMERCIAL - NEW | 08/21/2012 | COMPLETED |
08/21/2012 | RESUBMITTAL | 09/27/2012 | COMPLETED |
09/27/2012 | RESUBMITTAL | 10/18/2012 | COMPLETED |
10/18/2012 | RESUBMITTAL | 11/29/2012 | COMPLETED |
11/29/2012 | REVISION - - 1ST | 12/19/2012 | COMPLETED |
12/04/2012 | REVISION - - 2ND | 12/19/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM03657
Permit Status: C of o
Permit Description: NEW: TWO STORY CLUBHOUSE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/20/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM03657
Permit Description: NEW: TWO STORY CLUBHOUSE
Total Completed Inspections - 50
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/31/2012 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | 1. CABANA TO CODE PUMPING REDLINE CHANGES 2. TO CODE PENDING REDLINE CHANRGES |
10/31/2012 | PLUMBING - SEWER HCS CONNECT | RCAMACHO | Approved | IVRS - Inspection :* |
11/15/2012 | ELECTRIC - UFER | RCAMACHO | Approved | IVRS - Inspection :* |
11/15/2012 | BUILDING PRE-SLAB | RCAMACHO | Approved | IVRS - Inspection :* |
11/15/2012 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | IVRS - Inspection :* |
11/15/2012 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | IVRS - Inspection :* |
11/21/2012 | ELECTRIC - UNDERGROUND | RCAMACHO | Approved | IVRS - Inspection :* |
12/03/2012 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | DONE BY CAMACHO ON 11/30 |
01/30/2013 | ROOF NAILING | RCAMACHO | Approved | IVRS - Inspection :* |
01/30/2013 | EXT METAL CLIPS/EXT SHEATHING | RCAMACHO | Approved | IVRS - Inspection :* |
02/22/2013 | U VALUE FOR WINDOW | RCAMACHO | Approved | IVRS - Inspection :* |
02/22/2013 | STUCCO MESH | RCAMACHO | Approved | IVRS - Inspection :* |
04/05/2013 | SHEET ROCK NAILING | RCAMACHO | Approved | IVRS - Inspection :* |
04/25/2013 | ELECTRIC - CABLE DROP | RCAMACHO | Approved | IVRS - Inspection :* |
04/26/2013 | TEP CLEARANCE - AM | RCAMACHO | Approved | ECO |
05/31/2013 | FIRE SPKLR - OH PIPING & HYDRO | WMOTTO | Approved | |
05/31/2013 | FIRE SPKLR - UG PIPING FLUSH | WMOTTO | Approved | |
05/31/2013 | FIRE SPKLR - UG, PIPING, HYDRO | WMOTTO | Approved | |
06/18/2013 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
06/26/2013 | FIRE - FINAL | wmotto | Approved | |
06/26/2013 | FIRE - ALARM FINAL | wmotto | Approved | |
06/27/2013 | PLUMBING - PROGRESS | RCAMACHO | Approved | PER PLMB FINAL |
06/27/2013 | MECHANICAL - UNDERGROUND | RCAMACHO | Approved | PER MECH FINAL |
06/27/2013 | ELECTRIC - PROGRESS | RCAMACHO | Approved | PER ELEC FINAL |
06/27/2013 | ELECTRIC - TEMP POWER FOR TEST | RCAMACHO | Approved | PER ELEC FINAL |
06/27/2013 | ELECTRIC - CONSTRUCTION POWER | RCAMACHO | Approved | PER ELEC FINAL |
06/27/2013 | BUILDING - PROGRESS | RCAMACHO | Approved | PER BLDG FINAL |
06/27/2013 | PLUMBING - YARD WTR LINE/TEST | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | FRAMING | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | PLUMBING - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | PLUMBING - PRE SLAB | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | FIREWALL/FIREBARRIER/FIRESTOP | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | MECHANICAL - ABOVE CEILING | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | PLUMBING - ABOVE CEILING | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | ELECTRIC - ABOVE CEILING | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | BUILDING ABOVE CEILING | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | OUTDOOR LIGHTING FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | ELECTRIC - OUTDOOR LIGHTING | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | MECHANICAL - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | PLUMBING - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | ELECTRIC - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | BUILDING - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
06/27/2013 | ENGINEERING - FINAL | jgreen | Approved | |
07/01/2013 | NPPO - FINAL | RLEDONNE | Approved | |
07/01/2013 | SIGN - FINAL | RLEDONNE | Approved | |
07/01/2013 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
07/01/2013 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
07/02/2013 | RIGHT OF WAY - FINAL | PWHIDDON | Approved |