Permit: T12CM03391
Permit Details
Apply Date:
06/11/2012
Applicant:
MCCALEB CONSTRUCTION LLC
Description:
NEW SFR R1 - Sleeping quarters on top of garage
Contractors:
- MCCALEB CONSTRUCTION LLC
Permit Reviews
Permit Number - T12CM03391
Permit Status: Final
Permit Description: NEW SFR
R1 - Sleeping quarters on top of garage
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/11/2012 | PLANS OK TO SUBMIT - RES | 06/11/2012 | COMPLETED |
| 06/11/2012 | RESIDENTIAL - BLDG/WWM | 06/29/2012 | COMPLETED |
| 07/02/2012 | RESUBMITTAL | 07/02/2012 | COMPLETED |
| 07/16/2012 | REVISION - - 1ST | 07/16/2012 | COMPLETED |
| 08/28/2012 | REVISION - - 2ND | 08/28/2012 | COMPLETED |
| 08/28/2012 | REVISION - - 2ND | 09/07/2012 | COMPLETED |
| 09/07/2012 | REVISION - - 2ND | 09/07/2012 | COMPLETED |
| 09/14/2012 | REVISION - - 3RD | 09/14/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM03391
Permit Status: Final
Permit Description: NEW SFR
R1 - Sleeping quarters on top of garage
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/11/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T12CM03391
Permit Description: NEW SFR
R1 - Sleeping quarters on top of garage
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/01/2012 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | IVRS - Inspection :* |
| 08/01/2012 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | IVRS - Inspection :* |
| 08/01/2012 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | IVRS - Inspection :* |
| 08/07/2012 | ELECTRIC - UNDERGROUND | RMYERS | Approved | IVRS - Inspection :* |
| 08/07/2012 | ELECTRIC - UFER | RMYERS | Approved | IVRS - Inspection :* |
| 08/07/2012 | BUILDING PRE-SLAB | RMYERS | Approved | IVRS - Inspection :* |
| 08/07/2012 | EXCAVATION/LAYOUT REBAR & ZON | RMYERS | Approved | IVRS - Inspection :* |
| 08/10/2012 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | IVRS - Inspection :* |
| 08/10/2012 | ELECTRIC - CABLE DROP | DQUINN | Approved | IVRS - Inspection :* |
| 08/10/2012 | TEP CLEARANCE - AM | DQUINN | Approved | ECO |
| 09/18/2012 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 09/18/2012 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | IVRS - Inspection :* |
| 09/27/2012 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
| 09/27/2012 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 09/27/2012 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 09/27/2012 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 09/27/2012 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | IVRS - Inspection :* |
| 09/27/2012 | U VALUE FOR WINDOW | DQUINN | Approved | IVRS - Inspection :* |
| 09/27/2012 | STUCCO MESH | DQUINN | Approved | IVRS - Inspection :* |
| 10/04/2012 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 11/07/2012 | BUILDING - FINAL | DQUINN | Approved | |
| 11/07/2012 | MECHANICAL - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 11/07/2012 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 11/07/2012 | ELECTRIC - FINAL | RMYERS | Approved | IVRS - Inspection :* |