Permit: T11CM03594
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
1720 E SPEEDWAY BL
Address NEW:
1720 E SPEEDWAY BL
Apply Date:
11/22/2011
Applicant:
JAMES ROBERTSON
Description:
TI: RETAIL
Contractors:
- EPSTEIN CONSTRUCTION L L C
Permit Reviews
Permit Number - T11CM03594
Permit Status: C of o
Permit Description: TI: RETAIL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/26/2012 | REVISION - - 1ST | 01/26/2012 | COMPLETED |
| 02/24/2012 | REVISION - - 2ND | 02/24/2012 | COMPLETED |
| 11/22/2011 | COMMERCIAL - TI | 12/29/2011 | COMPLETED |
| 12/29/2011 | OTHER | 01/04/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM03594
Permit Status: C of o
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/22/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM03594
Permit Description: TI: RETAIL
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/31/2012 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
| 01/31/2012 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
| 02/02/2012 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
| 02/02/2012 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
| 02/22/2012 | FIRE - FINAL | DSIWARSKI | Approved | |
| 02/23/2012 | MECHANICAL - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 02/23/2012 | MECHANICAL - FINAL | AQUIROZ | Approved | IVRS - Inspection :* 1) NEED BALANCE REPORT |
| 02/23/2012 | NPPO - FINAL | MRUSSO | Approved | |
| 02/23/2012 | SIGN - FINAL | MRUSSO | Approved | |
| 02/23/2012 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 02/23/2012 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 02/24/2012 | HEALTH DEPT - FINAL 724-7908 | NRAMIREZ | Approved | PER INSP COPY |
| 02/24/2012 | BUILDING ABOVE CEILING | JBURGE | Approved | PER BL FINAL |
| 02/24/2012 | FRAMING | JBURGE | Approved | PER BLDG FINAL |
| 02/24/2012 | SHEET ROCK NAILING | JBURGE | Approved | PER BLDG FINAL |
| 02/24/2012 | BUILDING - FINAL | JBURGE | Approved | PER INSP COPY |
| 02/24/2012 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | PER ME FINAL |
| 02/24/2012 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | PER PL FINAL |
| 02/24/2012 | PLUMBING - GAS PRESS TEST FNL | JBURGE | Approved | PER PL FINAL |
| 02/24/2012 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | PER EL FINAL |
| 02/24/2012 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | PER EL FINAL |
| 02/24/2012 | ELECTRIC - FINAL | JBURGE | Approved | PER INSP CARD |
| 02/24/2012 | PLUMBING - PROGRESS | JBURGE | Approved | PER PL FINAL |
| 02/24/2012 | PLUMBING - FINAL | JBURGE | Approved | PER INSP CARD |