Permit: T11CM03528
Permit Details
Apply Date:
11/14/2011
Applicant:
ADOLF WHITTEN
Description:
NEW BEDROOM & BATH RELOCATION - RES
Permit Reviews
Permit Number - T11CM03528
Permit Status: Final
Permit Description: NEW BEDROOM & BATH RELOCATION - RES
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/07/2012 | REVISION - - 1ST | 05/07/2012 | COMPLETED |
| 11/14/2011 | RESIDENTIAL - BLDG/ZONING/ENGINE/WWM | 11/14/2011 | COMPLETED |
| 11/14/2011 | RESIDENTIAL - BLDG/WWM | 12/12/2011 | COMPLETED |
| 12/28/2011 | RESIDENTIAL - BLDG/WWM | 01/12/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM03528
Permit Status: Final
Permit Description: NEW BEDROOM & BATH RELOCATION - RES
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/14/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T11CM03528
Permit Description: NEW BEDROOM & BATH RELOCATION - RES
Total Completed Inspections - 16
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/13/2012 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | IVRS - Inspection :* |
| 01/17/2012 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* |
| 01/17/2012 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* |
| 03/15/2012 | ROOF NAILING | WLAHR | Approved | IVRS - Inspection :$ |
| 05/09/2012 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 05/09/2012 | PLUMBING - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 05/09/2012 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 05/09/2012 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
| 05/09/2012 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
| 05/09/2012 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 05/25/2012 | SHEET ROCK NAILING | WLAHR | Approved | IVRS - Inspection :* |
| 07/17/2013 | PLUMBING - FINAL | WLAHR | Approved | IVRS - Inspection :* |
| 07/23/2013 | EXT METAL CLIPS/EXT SHEATHING | WLAHR | Approved | PER BLDG FINAL - WLAHR |
| 07/23/2013 | MECHANICAL - FINAL | WLAHR | Approved | IVRS - Inspection :* |
| 07/23/2013 | ELECTRIC - FINAL | WLAHR | Approved | IVRS - Inspection :* |
| 07/23/2013 | BUILDING - FINAL | WLAHR | Approved | IVRS - Inspection :* |