Permit: T11CM03524
Permit Details
Apply Date:
11/14/2011
Applicant:
METRO TED
Description:
TI; RETAIL
Contractors:
- HORIZON RETAIL CONSTRUCTION INC
Permit Reviews
Permit Number - T11CM03524
Permit Status: C of o
Permit Description: TI; RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
11/14/2011 | COMMERCIAL - TI | 11/21/2011 | COMPLETED |
11/21/2011 | OTHER | 11/30/2011 | COMPLETED |
11/30/2011 | OTHER | 12/05/2011 | COMPLETED |
12/13/2011 | OTHER | 12/15/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM03524
Permit Status: C of o
Permit Description: TI; RETAIL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/14/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM03524
Permit Description: TI; RETAIL
Total Completed Inspections - 27
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/09/2011 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
12/09/2011 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
12/13/2011 | RIGHT OF WAY - FINAL | P.Whiddon | Approved | |
12/16/2011 | ENGINEERING - FINAL | MRUSSO | Approved | |
12/16/2011 | NPPO - FINAL | MRUSSO | Approved | |
12/16/2011 | SIGN - FINAL | MRUSSO | Approved | |
12/16/2011 | LANDSCAPE - FINAL | MRUSSO | Approved | |
12/19/2011 | BUILDING ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* 1) CANNOT USE DRYWALL SCREW FOR "L" BRACKET |
12/20/2011 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
12/21/2011 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR #108-M1 & M2 PER R. HOLLANDER |
12/27/2011 | FIRE SPKLR - FINAL | DSIWARSKI | Approved | PER SIGNED JOB CARD |
12/28/2011 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
12/29/2011 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
12/29/2011 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
12/29/2011 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
12/29/2011 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
12/30/2011 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* 1) REQUIRE METHOD OF STERILIZATION |
12/30/2011 | FIRE - FINAL | DSIWARSKI | Approved | Rear exit has panic hardware. Two actions are required to open door, must remove second door handle. |
12/30/2011 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
12/30/2011 | ELECTRIC - TEMPORARY SERVICE | RHOLLAND | Approved | IVRS - Inspection :* |
12/30/2011 | ELECTRIC - SERVICE UPGRADE | RHOLLAND | Approved | IVRS - Inspection :* |
12/30/2011 | ELECTRIC - PROGRESS | RHOLLAND | Approved | IVRS - Inspection :* |
12/30/2011 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
12/30/2011 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
12/30/2011 | BUILDING - FINAL | LHANLY | Approved | NOT READY. NEED FIRE AND TRADE FINALS BEFORE SCHEDULING BUILDING FINAL. |
01/03/2012 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | |
01/04/2012 | ELECTRIC - FINAL | AQUIROZ | Approved |