Permit: T11CM03501
Permit Details
Apply Date:
11/10/2011
Applicant:
RIO WEST DEVELOPMENT AND CONSTR *C*
Description:
INTERIOR RENOVATIONS EXISTING OFFICE & WAREHOUSE AND ENTRY PERGOLA ADDITION (4TH PHASE)
Contractors:
- RIO WEST DEVELOPMENT AND CONSTR *C*
Permit Reviews
Permit Number - T11CM03501
Permit Status: Final
Permit Description: INTERIOR RENOVATIONS EXISTING OFFICE & WAREHOUSE AND ENTRY PERGOLA ADDITION (4TH PHASE)
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/04/2012 | RESUBMITTAL - TI ALL | 05/11/2012 | COMPLETED |
05/11/2012 | RESUBMITTAL | 05/18/2012 | COMPLETED |
11/10/2011 | PLANS OK TO SUBMIT - COMM | 11/10/2011 | COMPLETED |
11/29/2011 | COMMERCIAL - TI | 01/26/2012 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T11CM03501
Permit Description: INTERIOR RENOVATIONS EXISTING OFFICE & WAREHOUSE AND ENTRY PERGOLA ADDITION (4TH PHASE)
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/23/2012 | PLUMBING - BACK WATER VALVE | BBENEDON | Approved | IVRS - Inspection :* |
06/04/2012 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | NPPO - FINAL | DROBERTS | Approved | |
12/11/2012 | SIGN - FINAL | DROBERTS | Approved | |
12/11/2012 | LANDSCAPE - FINAL | DROBERTS | Approved | |
12/11/2012 | ENGINEERING - FINAL | DROBERTS | Approved | |
12/11/2012 | MECHANICAL - FINAL | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | PLUMBING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | ELECTRIC - FINAL | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | PLUMBING - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | SITE - SEWER | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | PLUMBING - GAS PRESS TEST FNL | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | PLUMBING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | PLUMBING - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | PLUMBING - PRE SLAB | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | ELECTRIC - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* |
12/11/2012 | RIGHT OF WAY - FINAL | P.Whiddon | Approved | |
12/12/2012 | MECHANICAL - HYDRONIC PIPING | JBURGE | Approved | OK PER MECHANICAL FINAL |
12/18/2012 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | Found problems field will be given |
12/18/2012 | FIRE - FINAL | CSCHULTZ | Approved | Need to have approved plans reflect that no alarm system will be installed Per letter from Advantech engineering dated December 14, 2012. |
01/30/2013 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
02/01/2013 | BUILDING - PROGRESS | JBURGE | Approved | PER FINAL |