Permit: T11CM03166
Permit Details
Apply Date:
10/03/2011
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEW RETAIL BLDG
Architects:
- SCHICK, RICHARD HENRY
Permit Reviews
Permit Number - T11CM03166
Permit Status: C of o
Permit Description: NEW RETAIL BLDG
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/09/2012 | RESUBMITTAL | 01/12/2012 | COMPLETED |
01/12/2012 | RESUBMITTAL | 01/17/2012 | COMPLETED |
03/30/2012 | REVISION - - 1ST | 03/30/2012 | COMPLETED |
10/03/2011 | PLANS OK TO SUBMIT - COMM | 10/03/2011 | COMPLETED |
10/14/2011 | COMMERCIAL - NEW | 12/06/2011 | COMPLETED |
12/06/2011 | RESUBMITTAL | 12/27/2011 | COMPLETED |
12/27/2011 | RESUBMITTAL | 01/09/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM03166
Permit Status: C of o
Permit Description: NEW RETAIL BLDG
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/03/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM03166
Permit Description: NEW RETAIL BLDG
Total Completed Inspections - 46
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/09/2012 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
02/15/2012 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* |
02/16/2012 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* |
02/16/2012 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* |
02/16/2012 | PLUMBING - PRE SLAB | JBURGE | Approved | IVRS - Inspection :* |
03/29/2012 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* |
04/11/2012 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO COVER |
04/13/2012 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
04/17/2012 | FIRE SPKLR - UG, PIPING, HYDRO | CSCHULTZ | Approved | 200 PSI test for 2 hours and placment approved still needs to be flushed |
04/19/2012 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* |
04/26/2012 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
04/27/2012 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
04/27/2012 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
04/27/2012 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
05/02/2012 | FIRE SPKLR - OH PIPING & HYDRO | WMOTTO | Approved | |
05/02/2012 | FIRE SPKLR - UG PIPING FLUSH | WMOTTO | Approved | |
05/02/2012 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
05/08/2012 | TEP CLEARANCE - PM | JWEATHER | Approved | ECO CLEARED PER D. WALKER |
05/08/2012 | ELECTRIC - UFER | DWALKER | Approved | IVRS - Inspection :* |
05/08/2012 | ELECTRIC - TEMPORARY SERVICE | DWALKER | Approved | IVRS - Inspection :* |
05/11/2012 | PLUMBING - ROOF DRAINS | BBENEDON | Approved | IVRS - Inspection :* |
05/16/2012 | ELECTRIC - UNDERGROUND | JBURGE | Approved | IVRS - Inspection :* 1) LIGHT POLE CAISSON FOOTING AT SOUTH EAST CORNER OF BLDG, NORTH AND SOUTH SECURITY DOORS OK TO COVER PROGRESS AREAS |
05/18/2012 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
05/18/2012 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
05/22/2012 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
05/22/2012 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
05/23/2012 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
05/24/2012 | ELECTRIC - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
05/24/2012 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
05/24/2012 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
05/25/2012 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
05/25/2012 | PLUMBING - YARD WTR LINE/TEST | JBURGE | Approved | |
05/25/2012 | NPPO - FINAL | DROBERTS | Approved | |
05/25/2012 | SIGN - FINAL | DROBERTS | Approved | |
05/25/2012 | MECHANICAL - FINAL | JBURGE | Approved | IVRS - Inspection :* |
05/25/2012 | PLUMBING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
06/21/2012 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | IVRS - Inspection :* |
06/21/2012 | ELECTRIC - FINAL | JBURGE | Approved | IVRS - Inspection :* |
06/21/2012 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | IVRS - Inspection :* |
06/21/2012 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
06/22/2012 | BUILDING - PROGRESS | DWALKER | Approved | IVRS - Inspection :* |
06/26/2012 | FIRE - FINAL | CSCHULTZ | Approved | |
06/28/2012 | RIGHT OF WAY - FINAL | DROBERTS | Approved | |
06/28/2012 | LANDSCAPE - FINAL | DROBERTS | Approved | |
06/28/2012 | ENGINEERING - FINAL | DROBERTS | Approved | |
06/28/2012 | ZONING - FINAL | pgehlen | Approved | Revised DP approved |