Permit: T11CM02933
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
2462 N PANTANO RD #02
Address NEW:
2462 N PANTANO RD #02
Apply Date:
09/12/2011
Applicant:
FERNANDO BOJORQUEZ
Description:
TI: BARBER SHOP
Contractors:
- MEAD MEYER CONSTRUCTION INC
Permit Reviews
Permit Number - T11CM02933
Permit Status: C of o
Permit Description: TI: BARBER SHOP
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/12/2011 | COMMERCIAL - TI | 09/12/2011 | COMPLETED |
| 09/12/2011 | RESUBMITTAL | 09/14/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM02933
Permit Status: C of o
Permit Description: TI: BARBER SHOP
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/12/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM02933
Permit Description: TI: BARBER SHOP
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/15/2011 | RIGHT OF WAY - FINAL | P.Whiddon | Approved | |
| 09/16/2011 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* 1) DWV IN WALL TEST OK 2) PROVIDE 1/4" PER ROOT SLOPE AND SUPPORT AS REQUIRED 3) INSTALL CLEANOUT AND SAFETY PLATES AND T & P DRAIN 4) INSTALL FOAM WRAPS AT FLOOR PENETRATIONS |
| 09/16/2011 | SIGN - FINAL | MRUSSO | Approved | |
| 09/16/2011 | NPPO - FINAL | MRUSSO | Approved | |
| 09/16/2011 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 09/16/2011 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 09/26/2011 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
| 09/27/2011 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 09/30/2011 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* 1) PLEASE GIVE ME A CALL 2) NM ROMEX CABLE CAN BE USED IN WALLS BUT NOT IN A DROP TEE BAR CEILING 334.12 |
| 09/30/2011 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 10/05/2011 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
| 12/02/2011 | BUILDING - FINAL | JBURGE | Approved | |
| 12/02/2011 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 12/02/2011 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 12/02/2011 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 12/02/2011 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 12/06/2011 | FIRE - FINAL | WMOTTO | Approved | |
| 12/06/2011 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 12/06/2011 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
| 12/08/2011 | MECHANICAL - FINAL | JMILITEL | Approved |