Permit: T11CM02696
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
4745 E SPEEDWAY BL
Address NEW:
4745 E SPEEDWAY BL
Apply Date:
08/25/2011
Applicant:
N/A
Description:
TI: RETAIL
Architects:
- LARRY CLICK
Contractors:
- BRAXTON GROUP
Permit Reviews
Permit Number - T11CM02696
Permit Status: C of o
Permit Description: TI: RETAIL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/25/2011 | COMMERCIAL - TI | 08/26/2011 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T11CM02696
Permit Status: C of o
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/25/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM02696
Permit Description: TI: RETAIL
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/16/2011 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 09/19/2011 | SIGN - FINAL | MRUSSO | Approved | |
| 09/19/2011 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 09/19/2011 | RIGHT OF WAY - FINAL | P.Whiddon | Approved | |
| 09/19/2011 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* |
| 09/20/2011 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO SHEETROCK THROUGHOUT |
| 09/21/2011 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 09/22/2011 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 09/22/2011 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 09/22/2011 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 09/22/2011 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
| 09/22/2011 | NPPO - FINAL | MRUSSO | Approved | |
| 09/22/2011 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 09/23/2011 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 09/26/2011 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 09/26/2011 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 09/28/2011 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 09/28/2011 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
| 09/28/2011 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 09/28/2011 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
| 09/30/2011 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 09/30/2011 | FIRE - FINAL | DSIWARSKI | Approved |