Permit: T11CM02217
Permit Details
Apply Date:
07/13/2011
Applicant:
HEATHER MASTRANGELO
Description:
TI: INSTRUCTIONAL SCHOOL
Contractors:
- G AND J DEVELOPMENT INC ,
Permit Reviews
Permit Number - T11CM02217
Permit Status: C of o
Permit Description: TI: INSTRUCTIONAL SCHOOL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/13/2011 | COMMERCIAL - TI | 07/14/2011 | COMPLETED |
07/28/2011 | REVISION - - 1ST | 08/17/2011 | COMPLETED |
08/17/2011 | REVISION - - 2ND | 08/17/2011 | COMPLETED |
08/19/2011 | REVISION - - 3RD | 08/25/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM02217
Permit Status: C of o
Permit Description: TI: INSTRUCTIONAL SCHOOL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/13/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM02217
Permit Description: TI: INSTRUCTIONAL SCHOOL
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/29/2011 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
07/29/2011 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* |
08/03/2011 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
08/11/2011 | RIGHT OF WAY - FINAL | P. Whiddon | Approved | |
08/15/2011 | LANDSCAPE - FINAL | MRUSSO | Approved | |
08/18/2011 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO SET TILES 2) PLEASE CHECK ROOM #110-ROOF LEAK ? |
08/18/2011 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
08/18/2011 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
08/19/2011 | NPPO - FINAL | MRUSSO | Approved | |
08/19/2011 | SIGN - FINAL | MRUSSO | Approved | |
08/22/2011 | FIRE - FINAL | DSIWARSKI | Approved | |
08/22/2011 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
08/22/2011 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
08/22/2011 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
08/23/2011 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
08/23/2011 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
08/23/2011 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
08/23/2011 | ENGINEERING - FINAL | MRUSSO | Approved | |
08/24/2011 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
08/24/2011 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
08/25/2011 | FIRE SPKLR - FINAL | DSIWARSKI | Approved | |
08/25/2011 | BUILDING - FINAL | JBURGE | Approved | |
08/25/2011 | PLUMBING - FINAL | BBENEDON | Approved |