Permit: T11CM02025
Permit Details
Apply Date:
06/29/2011
Applicant:
CRAIG SCHUELTAR
Description:
ADD; 1 BEDROOM & 1 BATHROOM
Contractors:
- ANOTHER ROADRUNNER CONSTRUCTION LLC
Permit Reviews
Permit Number - T11CM02025
Permit Status: Final
Permit Description: ADD; 1 BEDROOM & 1 BATHROOM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/09/2012 | REVISION - - 1ST | 02/09/2012 | COMPLETED |
| 06/29/2011 | RESIDENTIAL - BLDG/ZONING/ENGINE/WWM | 08/23/2011 | COMPLETED |
| 08/23/2011 | RESIDENTIAL - BLDG/WWM | 10/14/2011 | COMPLETED |
| 10/14/2011 | RESUBMITTAL | 01/04/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM02025
Permit Status: Final
Permit Description: ADD; 1 BEDROOM & 1 BATHROOM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/29/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T11CM02025
Permit Description: ADD; 1 BEDROOM & 1 BATHROOM
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/20/2012 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
| 01/20/2012 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 01/26/2012 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
| 01/26/2012 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | IVRS - Inspection :* |
| 02/07/2012 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 02/08/2012 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | IVRS - Inspection :* |
| 02/22/2012 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* 1 OK TO CONNNECT NEW SYSTEM 2) CONRACTOR TO SOAP TEST FINAL CONNECTION |
| 02/29/2012 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
| 02/29/2012 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 02/29/2012 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 02/29/2012 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 03/09/2012 | SHEET ROCK NAILING | JMILITEL | Approved | IVRS - Inspection :* |
| 06/29/2012 | MECHANICAL - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 06/29/2012 | PLUMBING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 06/29/2012 | ELECTRIC - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 06/29/2012 | BUILDING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 06/29/2012 | U VALUE FOR WINDOW | DQUINN | Approved | IVRS - Inspection :* |