Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T11CM01952
Permit Details
Apply Date:
06/23/2011
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
TI: COLLISION CENTER
Architects:
- FRANKS, MICHAEL WILLIAM
Contractors:
- DIVISION II CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T11CM01952
Permit Status: C of o
Permit Description: TI: COLLISION CENTER
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/06/2012 | REVISION - - 2ND | 01/09/2012 | COMPLETED |
06/23/2011 | PLANS OK TO SUBMIT - COMM | 06/23/2011 | COMPLETED |
06/23/2011 | COMMERCIAL - TI | 07/19/2011 | COMPLETED |
08/10/2011 | RESUBMITTAL | 09/01/2011 | COMPLETED |
09/07/2011 | RESUBMITTAL | 09/15/2011 | COMPLETED |
09/15/2011 | RESUBMITTAL | 09/22/2011 | COMPLETED |
11/30/2011 | REVISION - - 1ST | 12/12/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM01952
Permit Status: C of o
Permit Description: TI: COLLISION CENTER
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/23/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM01952
Permit Description: TI: COLLISION CENTER
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/04/2011 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* 1) DEMO OF EXISTING BLDG |
11/17/2011 | SITE - SEWER | RMYERS | Approved | IVRS - Inspection :* |
11/17/2011 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
11/18/2011 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* 1) 4 F2 FOOTINGS; 2 F3 FOOTINGS; SOUTH EXTERIOR FOOTINGS; OK TO POUR PROGRESS AREAS |
11/22/2011 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* 1) SLAB PER DETAIL #2, PAGE S2.1, PAGE S2.1 OK TO POUR PROGRESS AREAS |
11/22/2011 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
12/01/2011 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* 1) CMU WALLS (ARCH-NORTH WALLS)-6 COLUMNS AT 16" OK TO GROUT |
12/01/2011 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* 1) CMU WALLS AND COLUMN STEMS |
12/01/2011 | PLUMBING - ROOF DRAINS | RMYERS | Approved | IVRS - Inspection :* 1) 2 SETS OF ROOF DRAINS AND OVERFLOW DRAINS INSTALLED IN COLUMNS OK TO COVER |
12/08/2011 | FRAMING | JBURGE | Approved | IVRS - Inspection :* 1) ALL AREAS EXCEPT NORTH WALL |
12/08/2011 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* 1) PARAPET AREAS; SE WALL OK TO COVER |
12/09/2011 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* 1) PROVIDE A TEST ON DWV 2) COMPLETE INTERMEDIATE PIPING PRIOR TO INSPECTION 3) PROVIDE APPROVED PLANS |
12/13/2011 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* 1) SUPPORT HORIZONTAL ABS OVERHEAD 2) SUPPORT VERTICAL ABS 3) JOB SITE TOO WET TO VERIFY WATER TEST 4) SEE NOTE #2 FROM 12/09/11 |
12/28/2011 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* 1) PROTECT ENDS OF VDV RACEWAYS FROM SHARP METAL EDGES 2) SUPPORT VDV CABLES IN WALLS 725.8 3) OK WALLS AFTER CORRECTIONS |
02/01/2012 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
02/01/2012 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* |
02/29/2012 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
03/05/2012 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER R. HOLLANDER |
03/12/2012 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | IVRS - Inspection :* |
03/12/2012 | PLUMBING - ABOVE CEILING | DQUINN | Approved | IVRS - Inspection :* |
03/12/2012 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | IVRS - Inspection :* |
03/12/2012 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
03/28/2012 | FIRE - FINAL | CSCHULTZ | Approved | |
03/28/2012 | PLUMBING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
03/28/2012 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
03/28/2012 | ELECTRIC - FINAL | JBURGE | Approved | IVRS - Inspection :* |
03/28/2012 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
03/29/2012 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |