Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Apply Date:
06/23/2011
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
TI: OFFICE
Architects:
  • MORROW, KEVIN THOMAS
Contractors:
  • CHESTNUT CONSTRUCTION CORPORATIO

Permit Reviews

Permit Number - T11CM01950
Permit Status: C of o
Permit Description: TI: OFFICE
Start Date Submittal Complete Date Status  
06/23/2011 COMMERCIAL - TI 06/24/2011 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T11CM01950
Permit Status: C of o
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
Date Name
06/23/2011 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T11CM01950
Permit Description: TI: OFFICE
Total Completed Inspections - 24
Date Description Inspector Results Comments
06/29/2011 FRAMING JBURGE Approved IVRS - Inspection :*
06/29/2011 ELECTRIC - INTERMEDIATE RMORENO Approved IVRS - Inspection :*
06/29/2011 ELECTRIC - UNDERGROUND RMORENO Approved IVRS - Inspection :*
06/30/2011 PLUMBING - ABOVE CEILING RRICH Approved IVRS - Inspection :*
06/30/2011 PLUMBING - INTERMEDIATE RRICH Approved IVRS - Inspection :*
07/01/2011 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
1) OK TO TAPE THROUGHOUT
07/19/2011 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
07/19/2011 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
07/21/2011 FIRE - FINAL WMOTTO Approved
07/21/2011 FIRE SPKLR - FINAL WMOTTO Approved
07/21/2011 BUILDING ABOVE CEILING GDABBS Approved IVRS - Inspection :*
07/21/2011 NPPO - FINAL JFEMLING Approved Approved
07/21/2011 SIGN - FINAL JFEMLING Approved Approved
07/21/2011 LANDSCAPE - FINAL JFEMLING Approved Approved
07/21/2011 ENGINEERING - FINAL JFEMLING Approved Approved
07/21/2011 RIGHT OF WAY - FINAL P.Whiddon Approved
07/22/2011 MECHANICAL - FINAL MRAMBER Approved IVRS - Inspection :*
1) AIR BALANCE REPORT DOES NOT MEET MINIMUM AIR FLOW ON TU-4 AND TU-5 OVER ALL AIR FLOW IS COMFORTABLE
2) SOME T.U. UNITS (EXISTING) NTO PERFORMING AS SPECIFIED, THESE ARE BEING REPAIRED
3) PROVIDE REVISED AIR BALANCE REPORT TO MECH. ENGINEER FOR FINAL APPROVAL
07/22/2011 PLUMBING - PROGRESS RRICH Approved IVRS - Inspection :*
08/25/2011 ELECTRIC - ABOVE CEILING RMORENO Approved
08/25/2011 PLUMBING - FINAL RRICH Approved IVRS - Inspection :*
08/25/2011 CERTIFICATE OF OCCUPANCY GDABBS Approved IVRS - Inspection :*
08/25/2011 BUILDING - FINAL GDABBS Approved IVRS - Inspection :*
08/25/2011 ELECTRIC - FINAL RMORENO Approved IVRS - Inspection :*
08/26/2011 PERMIT FINALED RMORENO Approved