Permit Details

Status:
C of o
Type:
COMMERCIAL ADDITION
Address NEW:
2160 E BROADWAY BL
Apply Date:
06/02/2011
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
ADDITION & TI: RETAIL
Architects:
  • GARCIA DAVID V
Contractors:
  • LECHNER CONSTRUCTION INC ,

Permit Reviews

Permit Number - T11CM01742
Permit Status: C of o
Permit Description: ADDITION & TI: RETAIL
Start Date Submittal Complete Date Status  
06/02/2011 PLANS OK TO SUBMIT - COMM 06/02/2011 COMPLETED Review Details
06/02/2011 PLANS OK TO SUBMIT - SITE 06/02/2011 COMPLETED Review Details
06/03/2011 COMMERCIAL - TI 06/20/2011 COMPLETED Review Details
06/03/2011 SITE 06/20/2011 COMPLETED Review Details
07/01/2011 RESUBMITTAL - TI ALL 07/19/2011 COMPLETED Review Details
07/01/2011 RESUBMITTAL - SITE ALL 07/19/2011 COMPLETED Review Details
07/20/2011 RESUBMITTAL 08/26/2011 COMPLETED Review Details
07/20/2011 RESUBMITTAL - SITE 08/26/2011 COMPLETED Review Details
09/20/2011 REVISION - - 1ST 10/05/2011 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T11CM01742
Permit Status: C of o
Permit Description: ADDITION & TI: RETAIL
Total Outstanding Activity Conditions - 1
Date Name
06/02/2011 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T11CM01742
Permit Description: ADDITION & TI: RETAIL
Total Completed Inspections - 30
Date Description Inspector Results Comments
08/10/2011 PLUMBING - ROUGH, SOIL RMYERS Approved IVRS - Inspection :*
08/11/2011 BUILDING PRE-SLAB GDABBS Approved IVRS - Inspection :*
08/26/2011 EXT METAL CLIPS/EXT SHEATHING MHENSON Approved IVRS - Inspection :*
09/06/2011 PLUMBING - PROGRESS RMYERS Approved IVRS - Inspection :*
09/06/2011 PLUMBING - INTERMEDIATE RMYERS Approved IVRS - Inspection :*
09/06/2011 STUCCO MESH MHENSON Approved IVRS - Inspection :*
09/06/2011 ELECTRIC - ABOVE CEILING DSANTACR Approved IVRS - Inspection :*
09/06/2011 ELECTRIC - INTERMEDIATE DSANTACR Approved IVRS - Inspection :*
09/07/2011 FRAMING MHENSON Approved IVRS - Inspection :*
09/07/2011 PLUMBING - ABOVE CEILING RMYERS Approved IVRS - Inspection :*
09/07/2011 PLUMBING - PRE SLAB RMYERS Approved IVRS - Inspection :*
09/12/2011 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
1) CONDENSATE IN WALL OK
09/15/2011 SHEET ROCK NAILING MHENSON Approved IVRS - Inspection :*
09/15/2011 EXCAVATION/LAYOUT REBAR & ZON MHENSON Approved IVRS - Inspection :*
09/19/2011 ROOF NAILING GDABBS Approved IVRS - Inspection :*
10/03/2011 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
10/03/2011 ELECTRIC - FINAL DSANTACR Approved
10/03/2011 ELECTRIC - UNDERGROUND DSANTACR Approved IVRS - Inspection :*
10/03/2011 RIGHT OF WAY - FINAL M.Otero Approved
10/03/2011 BUILDING - PROGRESS JBURGE Approved IVRS - Inspection :*
10/03/2011 U VALUE FOR WINDOW JBURGE Approved IVRS - Inspection :*
10/03/2011 BUILDING ABOVE CEILING JBURGE Approved IVRS - Inspection :*
10/04/2011 NPPO - FINAL JFEMLING Approved Approved
10/05/2011 PLUMBING - FINAL RMYERS Approved IVRS - Inspection :*
10/05/2011 FIRE - FINAL DSIWARSKI Approved
10/05/2011 SIGN - FINAL JFEMLING Approved Approved
10/05/2011 LANDSCAPE - FINAL JFEMLING Approved Approved
10/05/2011 ENGINEERING - FINAL JFEMLING Approved Approved
10/06/2011 MECHANICAL - FINAL LHANLY Approved
10/07/2011 BUILDING - FINAL GDABBS Approved IVRS - Inspection :*