Permit: T11CM01066
Permit Details
Apply Date:
04/12/2011
Applicant:
MARIA R VEDINGER
Description:
TI: GLHN OFFICE
Architects:
- GRIGSBY, DAVID CECIL
Contractors:
- HICKAM ARNOLD AND ASSOCIATES L L C
Permit Reviews
Permit Number - T11CM01066
Permit Status: C of o
Permit Description: TI: GLHN OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/12/2011 | PLANS OK TO SUBMIT - COMM | 04/12/2011 | COMPLETED |
04/12/2011 | COMMERCIAL - TI | 05/25/2011 | COMPLETED |
05/25/2011 | RESUBMITTAL | 06/22/2011 | COMPLETED |
06/22/2011 | RESUBMITTAL | 07/12/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM01066
Permit Status: C of o
Permit Description: TI: GLHN OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/12/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM01066
Permit Description: TI: GLHN OFFICE
Total Completed Inspections - 27
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/14/2011 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* 1) NORTH WALL-2 WINDOW SECTIONS DETAIL D4, PAGE A512-OK TO GROUT PROGRESS AREA |
09/20/2011 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* |
09/20/2011 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
09/20/2011 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
10/12/2011 | PLUMBING - ROOF DRAINS | BBENEDON | Approved | IVRS - Inspection :* |
10/27/2011 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* 1) OK RESTROOM 2) OK WALLS/HARD LIDS ROOMS #101 & 102 |
11/01/2011 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* |
11/17/2011 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
11/17/2011 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
11/17/2011 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
11/18/2011 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
11/18/2011 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
11/18/2011 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
12/05/2011 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
12/16/2011 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
12/16/2011 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
12/21/2011 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* 1) OK ABOVE CEILING |
12/29/2011 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
12/30/2011 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* 1) CANCELLED |
01/05/2012 | FIRE - FINAL | CSCHULTZ | Approved | |
01/06/2012 | ENGINEERING - FINAL | MRUSSO | Approved | |
01/06/2012 | NPPO - FINAL | MRUSSO | Approved | |
01/06/2012 | LANDSCAPE - FINAL | MRUSSO | Approved | |
01/06/2012 | SIGN - FINAL | MRUSSO | Approved | |
01/09/2012 | CERTIFICATE OF OCCUPANCY | AQUIROZ | Approved | |
01/09/2012 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
01/10/2012 | RIGHT OF WAY - FINAL | PWHIDDON | Approved |