Permit: T11CM00957
Permit Details
Status:
Final
Type:
COMMERCIAL ALTERATION
Address:
3566 E SPEEDWAY BL
Address NEW:
3566 E SPEEDWAY BL
Apply Date:
04/01/2011
Applicant:
N/A
Description:
TI: AUTO SALES
Architects:
- MOORE CHARLES SAMUEL
Contractors:
- DIVISION II CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T11CM00957
Permit Status: Final
Permit Description: TI: AUTO SALES
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/01/2011 | PLANS OK TO SUBMIT - COMM | 04/01/2011 | COMPLETED |
| 04/01/2011 | COMMERCIAL - TI | 04/29/2011 | COMPLETED |
| 04/29/2011 | RESUBMITTAL | 05/18/2011 | COMPLETED |
| 05/18/2011 | RESUBMITTAL | 05/19/2011 | COMPLETED |
| 07/21/2011 | REVISION - - 1ST | 12/22/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM00957
Permit Status: Final
Permit Description: TI: AUTO SALES
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/01/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T11CM00957
Permit Description: TI: AUTO SALES
Total Completed Inspections - 30
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/07/2011 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* 1) ROOF DRAIN AND OVERFLOWS OK 2) CONTRACTOR TO ADD HANGERS AS REQUIRED |
| 07/19/2011 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* 1) ROOF SYSTEM COMPLETE; EXTERIOR SHEATHING COMPLETE |
| 07/29/2011 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* 1) NOTE: WC-1 STILL REQUIRES A 1" WATER SERVICE |
| 09/20/2011 | RIGHT OF WAY - FINAL | M.Otero | Approved | |
| 09/20/2011 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 09/20/2011 | NPPO - FINAL | MRUSSO | Approved | |
| 09/20/2011 | SIGN - FINAL | MRUSSO | Approved | |
| 10/06/2011 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 10/18/2011 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
| 10/18/2011 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 10/20/2011 | ELECTRIC - UNDERGROUND | RMORENO | Approved | IVRS - Inspection :* |
| 10/28/2011 | FRAMING | JBURGE | Approved | IVRS - Inspection :* 1) SHOWROOM COMPLETE |
| 10/28/2011 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* 1) EXTERIOR STEM WALLS |
| 12/01/2011 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
| 12/08/2011 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 12/08/2011 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 12/08/2011 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 12/08/2011 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
| 12/08/2011 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 12/08/2011 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
| 12/08/2011 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* |
| 12/13/2011 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
| 12/13/2011 | ELECTRIC - PROGRESS | RMORENO | Approved | |
| 12/13/2011 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* |
| 12/13/2011 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 12/16/2011 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* 1) EF-1 THRU 6 HAVE HAD THE VALVES CHANGED, ALTHOUGH NEGATIVE PRESSURE IS STILL MAINTAINED 2) AIR BALANCE REPORT REFLECTS LOW AIR BLOWS. ALTHOUGH NOT CHANGES WERE MADE TO THE MECHANICAL SYSTEM WITH THE EXCEPTION OF REGISTER REPLACEMENT 3) PROVIDE A COPY OF THE REPORT TO THE ENGINEER FOR REVIEW AND RECOMMENDATIONS 4) NO LIFE SAFETY ISSUES OBSERVED |
| 12/16/2011 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 12/20/2011 | FIRE - FINAL | WMOTTO | Approved | |
| 12/20/2011 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/20/2011 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |