Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T11CM00870
Permit Details
Apply Date:
03/23/2011
Applicant:
N/A
Description:
NEW APT BLDG 5 STORY - BLDG 3
Contractors:
- CONSTRUCTION ENTERPRISES INC
Permit Reviews
Permit Number - T11CM00870
Permit Status: C of o
Permit Description: NEW APT BLDG 5 STORY - BLDG 3
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/23/2011 | PLANS OK TO SUBMIT - COMM | 03/23/2011 | COMPLETED |
03/23/2011 | COMMERCIAL - NEW | 04/29/2011 | COMPLETED |
04/29/2011 | RESUBMITTAL - TI ALL | 05/24/2011 | COMPLETED |
05/24/2011 | RESUBMITTAL | 06/23/2011 | COMPLETED |
09/01/2011 | REVISION - - 1ST | 09/01/2011 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T11CM00870
Permit Status: C of o
Permit Description: NEW APT BLDG 5 STORY - BLDG 3
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/23/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM00870
Permit Description: NEW APT BLDG 5 STORY - BLDG 3
Total Completed Inspections - 38
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/30/2011 | PLUMBING - ROUGH, SOIL | LHANLY | Approved | |
09/30/2011 | STEM WALL/RETAINING WALL | LHANLY | Approved | |
09/30/2011 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | |
11/30/2011 | ROOF NAILING | LHANLY | Approved | 2ND AND 3RD FLOOR JOIST SYSTEMS |
11/30/2011 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | |
12/05/2011 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | Temporary standpipes install and 200 psi test approved on alley side Temporary standpipes install and within 100 of a fire hydrant and 200 psi test approved on 6th street side |
12/08/2011 | FRAMING | DQUINN | Approved | IVRS - Inspection :* BLDG 3 1ST FLOOR: 1) ALL H.D.'S IN PLACE. ALL 1ST TO 2ND FLOOR STRAPPING IS IN PLACE 2) WHAT IS THE FIX FOR UN-TAUGHT STRAPS ? 3) FHA STRAPS (INSTEAD OF BANG PLATES) NEEDED AT OVER BORES IN PLUMBING BEARING WALLS ? |
12/08/2011 | FRAMING | LHANLY | Approved | |
12/12/2011 | BUILDING - PROGRESS | LHANLY | Approved | MASONRY FIRE-WALL TO 12' |
12/12/2011 | FIREWALL/FIREBARRIER/FIRESTOP | LHANLY | Approved | MASONRY FIRE-WALL TO 12' |
12/28/2011 | PLUMBING - PRE SLAB | LHANLY | Approved | |
12/28/2011 | BUILDING PRE-SLAB | LHANLY | Approved | |
03/07/2012 | STUCCO MESH | DQUINN | Approved | IVRS - Inspection :* |
04/11/2012 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* 1) BLDG 3-4TH & 5TH FLOORS (CRANE UNITS) OK |
05/15/2012 | MECHANICAL - PROGRESS | LHANLY | Approved | |
05/15/2012 | MECHANICAL - ABOVE CEILING | LHANLY | Approved | |
05/15/2012 | MECHANICAL - INTERMEDIATE | LHANLY | Approved | |
05/15/2012 | MECHANICAL - INTERMEDIATE | LHANLY | Approved | |
05/15/2012 | ELECTRIC - UNDERGROUND | LHANLY | Approved | |
05/15/2012 | U VALUE FOR WINDOW | LHANLY | Approved | |
05/15/2012 | BUILDING ABOVE CEILING | LHANLY | Approved | |
06/22/2012 | FIRE SPKLR - UG, PIPING, HYDRO | WMOTTO | Approved | |
07/05/2012 | MECHANICAL - FINAL | LHANLY | Approved | |
07/05/2012 | PLUMBING - FINAL | LHANLY | Approved | |
07/05/2012 | PLUMBING - PROGRESS | LHANLY | Approved | |
07/05/2012 | PLUMBING - SEWER HCS CONNECT | LHANLY | Approved | |
07/05/2012 | PLUMBING - YARD WTR LINE/TEST | LHANLY | Approved | |
07/05/2012 | PLUMBING - ROOF DRAINS | LHANLY | Approved | |
07/05/2012 | PLUMBING - ABOVE CEILING | LHANLY | Approved | |
07/05/2012 | PLUMBING - INTERMEDIATE | LHANLY | Approved | |
07/05/2012 | ELECTRIC - FINAL | LHANLY | Approved | |
07/05/2012 | ELECTRIC - OUTDOOR LIGHTING | LHANLY | Approved | |
07/05/2012 | ELECTRIC - PROGRESS | LHANLY | Approved | |
07/05/2012 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | |
07/17/2012 | FIRE - FINAL | WMOTTO | Approved | |
07/17/2012 | FIRE - ALARM FINAL | WMOTTO | Approved | |
07/17/2012 | FIRE - LANE SIGNS | WMOTTO | Approved | |
07/17/2012 | BUILDING - FINAL | LHANLY | Approved |