Permit: T11CM00218
Permit Details
Apply Date:
01/26/2011
Applicant:
N/A
Description:
TI:MANUFACTURING
Architects:
- RAWSON, RHONDA LEE
Contractors:
- M A S DEVELOPMENT INC *APA*
Permit Reviews
Permit Number - T11CM00218
Permit Status: Final
Permit Description: TI:MANUFACTURING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/26/2011 | COMMERCIAL - TI | 01/28/2011 | COMPLETED |
| 01/28/2011 | OTHER | 02/01/2011 | COMPLETED |
| 02/22/2011 | REVISION - - 1ST | 02/22/2011 | COMPLETED |
| 05/11/2011 | REVISION - - 2ND | 05/11/2011 | COMPLETED |
| 06/24/2011 | REVISION - - 3RD | 06/24/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM00218
Permit Status: Final
Permit Description: TI:MANUFACTURING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/26/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T11CM00218
Permit Description: TI:MANUFACTURING
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/14/2011 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
| 03/14/2011 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
| 03/14/2011 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* |
| 04/28/2011 | FRAMING | MHENSON | Approved | IVRS - Inspection :* |
| 05/13/2011 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* |
| 05/17/2011 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :$ |
| 05/17/2011 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
| 05/20/2011 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
| 05/20/2011 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
| 06/21/2011 | FIRE - FINAL | WMOTTO | Approved | |
| 06/21/2011 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
| 06/21/2011 | NPPO - FINAL | RDLD | Approved | NA FOR NPPO ON THIS JOB SITE. |
| 06/21/2011 | LANDSCAPE - FINAL | RDLD | Approved | NA FOR LANDSCAPE ON THIS SITE. |
| 06/21/2011 | ENGINEERING - FINAL | RDLD | Approved | |
| 06/21/2011 | PLUMBING - FINAL | LHANLY | Approved | STERILIZATION REPORT PROVIDED. REFEE WAS PAIS ON 5/11 |
| 06/22/2011 | SIGN - FINAL | MHENSON | Approved | IVRS - Inspection :* |
| 06/24/2011 | BUILDING - FINAL | LHANLY | Approved | |
| 09/14/2011 | PERMIT FINALED | JWEATHER | Approved |