Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T11CM00163
Permit Details
Apply Date:
01/20/2011
Applicant:
N/A
Description:
TI:RESIDENTIAL CARE FACILITY:CHANGE OF OCCUPANCY
Contractors:
- ATKINSON AND ASSOCIATES INC
Permit Reviews
Permit Number - T11CM00163
Permit Status: C of o
Permit Description: TI:RESIDENTIAL CARE FACILITY:CHANGE OF OCCUPANCY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/20/2011 | COMMERCIAL - TI | 05/10/2011 | COMPLETED |
05/10/2011 | RESUBMITTAL | 05/31/2011 | COMPLETED |
06/27/2011 | SITE | 07/13/2011 | COMPLETED |
07/13/2011 | REVISION - - 1ST | 07/13/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM00163
Permit Status: C of o
Permit Description: TI:RESIDENTIAL CARE FACILITY:CHANGE OF OCCUPANCY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/20/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM00163
Permit Description: TI:RESIDENTIAL CARE FACILITY:CHANGE OF OCCUPANCY
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/24/2011 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* 1) 6 COLUMN FOOTINGS OK TO POUR |
06/09/2011 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* |
06/15/2011 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
06/15/2011 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
06/15/2011 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* |
06/23/2011 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* ALL INTERMEDIATE OK RECALL FOR CLOSET FINALS |
07/14/2011 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
07/19/2011 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
07/19/2011 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
08/04/2011 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
08/17/2011 | NPPO - FINAL | DROBERTS | Approved | |
08/17/2011 | SIGN - FINAL | DROBERTS | Approved | |
08/17/2011 | LANDSCAPE - FINAL | DROBERTS | Approved | |
08/17/2011 | ENGINEERING - FINAL | DROBERTS | Approved | |
08/17/2011 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
08/17/2011 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
08/17/2011 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* |
08/17/2011 | RIGHT OF WAY - FINAL | P.Whiddon | Approved | |
08/19/2011 | FIRE - FINAL | WMOTTO | Approved | |
08/19/2011 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
08/19/2011 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
08/19/2011 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
08/23/2011 | MECHANICAL - ABOVE CEILING | LHANLY | Approved | |
08/23/2011 | MECHANICAL - INTERMEDIATE | LHANLY | Approved | |
08/23/2011 | ELECTRIC - ABOVE CEILING | LHANLY | Approved | |
08/23/2011 | FIREWALL/FIREBARRIER/FIRESTOP | LHANLY | Approved | |
08/23/2011 | U VALUE FOR WINDOW | LHANLY | Approved | |
08/23/2011 | BUILDING ABOVE CEILING | LHANLY | Approved |