Permit: T11CM00095
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
1310 W MIRACLE MILE #140
Address NEW:
1310 W MIRACLE MILE #140
Apply Date:
01/13/2011
Applicant:
N/A
Description:
TI:POLICE STATION; IMPOUND
Architects:
- MICKELBERG, PAUL DAVID
Contractors:
- WITHERS CONSTRUCTION L C , D L
Permit Reviews
Permit Number - T11CM00095
Permit Status: C of o
Permit Description: TI:POLICE STATION; IMPOUND
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/13/2011 | COMMERCIAL - TI | 01/14/2011 | COMPLETED |
| 01/14/2011 | COMMERCIAL - TI | 02/08/2011 | COMPLETED |
| 03/02/2011 | RESUBMITTAL | 03/14/2011 | COMPLETED |
| 03/14/2011 | RESUBMITTAL | 05/04/2011 | COMPLETED |
| 04/11/2011 | REVISION - - 1ST | 05/11/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM00095
Permit Status: C of o
Permit Description: TI:POLICE STATION; IMPOUND
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/13/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM00095
Permit Description: TI:POLICE STATION; IMPOUND
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/04/2011 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 08/04/2011 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 08/11/2011 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 08/11/2011 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 08/24/2011 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
| 08/26/2011 | FIRE - FINAL | WMOTTO | Approved | |
| 08/26/2011 | FIRE - ALARM FINAL | WMOTTO | Approved | |
| 09/12/2011 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 09/13/2011 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
| 09/13/2011 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
| 09/14/2011 | MECHANICAL - HYDRONIC PIPING | MRAMBER | Approved | IVRS - Inspection :* |
| 09/16/2011 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 09/16/2011 | RIGHT OF WAY - FINAL | M.Otero | Approved | |
| 09/16/2011 | SIGN - FINAL | MRUSSO | Approved | |
| 09/16/2011 | NPPO - FINAL | MRUSSO | Approved | |
| 09/16/2011 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 09/19/2011 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 09/20/2011 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 09/20/2011 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |