Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Final
Type:
Grading
Apply Date:
08/17/2011
Applicant:
BRIGHT, RICK LANE
Description:
REMODEL existing drainage under an existing pedestrian sidewalk. Remodel is to also fix foundation problems due to settling.
Architects:
  • BRIGHT, RICK LANE
Contractors:
  • HYMARK CONSTRUCTION ASSOCIATES L L C

Permit Reviews

Permit Number - T11BU01068
Permit Status: Final
Permit Description: REMODEL existing drainage under an existing pedestrian sidewalk. Remodel is to also fix foundation problems due to settling.
Start Date Submittal Complete Date Status  
08/17/2011 GRADING 08/17/2011 COMPLETED Review Details
08/17/2011 GRADING 08/26/2011 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T11BU01068
Permit Status: Final
Permit Description: REMODEL existing drainage under an existing pedestrian sidewalk. Remodel is to also fix foundation problems due to settling.
Total Outstanding Activity Conditions - 1
Date Name
08/17/2011 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T11BU01068
Permit Description: REMODEL existing drainage under an existing pedestrian sidewalk. Remodel is to also fix foundation problems due to settling.
Total Completed Inspections - 9
Date Description Inspector Results Comments
09/06/2011 ENGINEERING PRE-CONSTRUCTION MRUSSO Approved NO ONE CALLED AN INSPECTION IN FOR A PRE-CON MEETING.
FIRST INSPECTION ON SITE WAS FOR INTERMEDIATE GRADING. 9/1/11
09/07/2011 GRADING - TIER REV jgreen Approved Applicant brought the approved plans back in and made the changes as shown with clouded revisions. 1) solid concrete with rebar instead of the grouted CMU; 2) 4-inch down spouts extend thru the headwall and no longer tie intot he 18-inch piper (per Bob Sherry); and 3) Both invert elevations for u/s and d/s ends have been added, slope is now 1.4% not the 1.2%.
09/08/2011 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
1) HDPE IS NOT APPROVED UNDER A BLDG, PLEASE SEE RWS FOR CLARIFICATION
09/08/2011 PLUMBING - GAS PRESS TEST FNL BBENEDON Approved IVRS - Inspection :*
09/08/2011 PLUMBING - GAS PRESSURE TEST BBENEDON Approved IVRS - Inspection :*
09/08/2011 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
09/08/2011 GRADING - INTERMEDIATE MRUSSO Approved 1) STORM WATER CONVEYANCE PIPE IN PLACE.
2) ROOF DRAINS HAVE BEEN INSTALLED
3) ENSURE AN ELEVATION READING IS TAKEN AT THE INLET AND OUTLET TO STORM DRAIN PIPE.
4) OK TO BACKFILL
5) ENSURE CHANGES MADE TO ORIGINAL GRADING PLAN IS APPROVED.
11/02/2011 PLUMBING - ROUGH, SOIL BBENEDON Approved IVRS - Inspection :*
1) EAST SIDE SHOWER DEMO, ADD TOILETS DWV OK
08/24/2012 GRADING - FINAL DROBERTS Approved

Documents

File Name Document Type  
001_S4.2.TIF GRADING PLANS VIEW
002_C1.0.TIF GRADING PLANS VIEW
None DOCUMENTS VIEW