Permit: T10CM02591
Permit Details
Apply Date:
09/16/2010
Applicant:
N/A
Description:
ADD DETACHED SLEEPING QUARTERS
Contractors:
- REPP ENTERPRISES
Permit Reviews
Permit Number - T10CM02591
Permit Status: Expired
Permit Description: ADD DETACHED SLEEPING QUARTERS
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/16/2010 | PLANS OK TO SUBMIT - RES | 09/16/2010 | COMPLETED |
| 09/16/2010 | RESIDENTIAL BLDG/WWM | 10/27/2010 | COMPLETED |
| 10/27/2010 | RESUBMITTAL | 12/03/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM02591
Permit Status: Expired
Permit Description: ADD DETACHED SLEEPING QUARTERS
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 09/16/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 11/09/2010 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
Completed Inspections
Permit Status: Expired
Permit Number: T10CM02591
Permit Description: ADD DETACHED SLEEPING QUARTERS
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/06/2010 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | IVRS - Inspection :* 1) YARD WATER OK TO BACKFILL TO COPPER CONNECTIONS |
| 12/08/2010 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
| 12/08/2010 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | IVRS - Inspection :* |
| 12/16/2010 | ELECTRIC - UNDERGROUND | DQUINN | Approved | |
| 12/16/2010 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 12/28/2010 | REINFORCED MASONRY PRE-GROUT | DQUINN | Approved | IVRS - Inspection :* |
| 12/28/2010 | REINFORCED MASONRY PRE-GROUT | IVR USER | Approved | IVRS - RI canceled |
| 01/11/2011 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 02/15/2011 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
| 02/15/2011 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 02/15/2011 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 02/23/2011 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 04/26/2011 | MECHANICAL - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 04/26/2011 | PLUMBING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 04/26/2011 | ELECTRIC - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 04/27/2011 | BUILDING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 04/20/2017 | U VALUE FOR WINDOW | DQUINN | Approved | |
| 04/20/2017 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved |