Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Apply Date:
09/09/2010
Applicant:
N/A
Description:
"GHOST RANCH LODGE"-BUILDING 12
Contractors:
  • FOUR LEAF CONSTRUCTION INC

Permit Reviews

Permit Number - T10CM02531
Permit Status: C of o
Permit Description: "GHOST RANCH LODGE"-BUILDING 12
Start Date Submittal Complete Date Status  
09/09/2010 PLANS OK TO SUBMIT - COMM 09/09/2010 COMPLETED Review Details
09/09/2010 COMMERCIAL NEW 10/13/2010 COMPLETED Review Details
11/03/2010 RESUBMITTAL 11/24/2010 COMPLETED Review Details
11/15/2010 OTHER 11/24/2010 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T10CM02531
Permit Status: C of o
Permit Description: "GHOST RANCH LODGE"-BUILDING 12
Total Outstanding Activity Conditions - 1
Date Name
09/09/2010 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T10CM02531
Permit Description: "GHOST RANCH LODGE"-BUILDING 12
Total Completed Inspections - 43
Date Description Inspector Results Comments
12/08/2010 ELECTRIC - UFER DSANTACR Approved IVRS - Inspection :*
12/13/2010 ELECTRIC - UNDERGROUND DSANTACR Approved IVRS - Inspection :*
12/17/2010 EXCAVATION/LAYOUT REBAR & ZON AQUIROZ Approved IVRS - Inspection :*
12/21/2010 ELECTRIC - CABLE DROP DSANTACR Approved IVRS - Inspection :*
1) OK REMAINDER TRENCH AND CONDUITS FOR TEMP POWER SITE LTG. AT BLDG #12
12/23/2010 STEM WALL/RETAINING WALL JBURGE Approved IVRS - Inspection :*
1) WEST HALF OF BLDG-STEM WALL
12/30/2010 PLUMBING - ROUGH, SOIL RMYERS Approved IVRS - Inspection :*
1) RAIN
01/05/2011 PLUMBING - PRE SLAB RMYERS Approved IVRS - Inspection :*
01/06/2011 PLUMBING - SEWER HCS CONNECT RRICH Approved IVRS - Inspection :*
02/24/2011 PLUMBING - YARD WTR LINE/TEST RMYERS Approved IVRS - Inspection :*
03/07/2011 PLUMBING - ROOF DRAINS RMYERS Approved IVRS - Inspection :*
03/08/2011 PLUMBING - ABOVE CEILING RMYERS Approved IVRS - Inspection :*
03/15/2011 FRAMING AQUIROZ Approved IVRS - Inspection :*
03/15/2011 ROOF NAILING AQUIROZ Approved IVRS - Inspection :*
03/21/2011 ELECTRIC - INTERMEDIATE RHOLLAND Approved IVRS - Inspection :*
1) OK 1ST FLOOR
03/21/2011 ELECTRIC - ABOVE CEILING RHOLLAND Approved IVRS - Inspection :*
03/23/2011 FIREWALL/FIREBARRIER/FIRESTOP AQUIROZ Approved IVRS - Inspection :*
03/23/2011 BUILDING ABOVE CEILING AQUIROZ Approved IVRS - Inspection :*
03/28/2011 STUCCO MESH AQUIROZ Approved IVRS - Inspection :*
04/07/2011 PLUMBING - INTERMEDIATE RMYERS Approved IVRS - Inspection :*
04/07/2011 PLUMBING - PROGRESS RMYERS Approved IVRS - Inspection :*
04/20/2011 TEP CLEARANCE - AM JWEATHER Approved TMPP CLEARED FOR #12101,12102,12103,12104,12105,12106,12107,12108,22101,22102,22103,22104,22105,22106 & 22107 PER R. HOLLANDER
04/26/2011 SIGN - FINAL JYBARRA Approved
04/26/2011 RIGHT OF WAY - FINAL M.Otero Approved
04/27/2011 FIRE SPKLR - FINAL DSIWARSKI Approved
04/27/2011 FIRE - FINAL DSIWARSKI Approved
04/27/2011 MECHANICAL - FINAL MRAMBER Approved IVRS - Inspection :*
04/27/2011 MECHANICAL - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
04/27/2011 OUTDOOR LIGHTING FINAL RHOLLAND Approved IVRS - Inspection :*
04/27/2011 ELECTRIC - FINAL RHOLLAND Approved IVRS - Inspection :*
04/27/2011 ELECTRIC - OUTDOOR LIGHTING RHOLLAND Approved IVRS - Inspection :*
04/27/2011 ELECTRIC - PROGRESS RHOLLAND Approved IVRS - Inspection :*
04/27/2011 ELECTRIC - TEMP POWER FOR TEST RHOLLAND Approved IVRS - Inspection :*
04/28/2011 ELECTRIC - TEMPORARY SERVICE AQUIROZ Approved
04/28/2011 PLUMBING - FINAL AQUIROZ Approved
04/28/2011 CERTIFICATE OF OCCUPANCY AQUIROZ Approved IVRS - Inspection :*
04/28/2011 BUILDING - FINAL AQUIROZ Approved IVRS - Inspection :*
04/28/2011 BUILDING PRE-SLAB AQUIROZ Approved IVRS - Inspection :*
04/28/2011 REINFORCED MASONRY PRE-GROUT AQUIROZ Approved IVRS - Inspection :*
04/28/2011 BUILDING - PROGRESS AQUIROZ Approved IVRS - Inspection :*
04/28/2011 SHEET ROCK NAILING AQUIROZ Approved IVRS - Inspection :*
04/28/2011 NPPO - FINAL MRUSSO Approved
04/28/2011 LANDSCAPE - FINAL MRUSSO Approved
04/28/2011 ENGINEERING - FINAL MRUSSO Approved

Documents

File Name Document Type  
C OF O_04-28-2011.TIF CERT OF OCC VIEW
None DOCUMENTS VIEW