Permit: T10CM01561
Permit Details
Apply Date:
06/09/2010
Applicant:
N/A
Description:
NEW GASOLINE CANOPY
Contractors:
- LANG WYATT CONSTRUCTION ,
Permit Reviews
Permit Number - T10CM01561
Permit Status: Final
Permit Description: NEW GASOLINE CANOPY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/09/2010 | PLANS OK TO SUBMIT - COMM | 06/10/2010 | COMPLETED |
06/10/2010 | COMMERCIAL-BLDG/FIRE/ZONING/ENG | 07/27/2010 | COMPLETED |
06/22/2010 | OTHER | 07/27/2010 | COMPLETED |
07/27/2010 | RESUBMITTAL | 10/05/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM01561
Permit Status: Final
Permit Description: NEW GASOLINE CANOPY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/09/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T10CM01561
Permit Description: NEW GASOLINE CANOPY
Total Completed Inspections - 19
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/20/2010 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
11/16/2010 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* 1) DRY PACK OK |
11/16/2010 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* |
11/18/2010 | FRAMING | MHENSON | Approved | IVRS - Inspection :* CANOPY SHEATHING |
12/06/2010 | STEM WALL/RETAINING WALL | MHENSON | Approved | IVRS - Inspection :* |
12/28/2010 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* |
12/30/2010 | PLUMBING - ROOF DRAINS | RLEDONNE | Approved | IVRS - Inspection :* 1) ROOF DRAIN PIPING STUB OUT OF CANOPY TEST OK |
03/22/2011 | PLUMBING - INTERMEDIATE | RMYERS | Approved | |
03/22/2011 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
04/05/2011 | FIRE - FINAL | CFUNKE | Approved | |
04/07/2011 | BUILDING - PROGRESS | MHENSON | Approved | IVRS - Inspection :* |
04/08/2011 | EXT METAL CLIPS/EXT SHEATHING | MHENSON | Approved | |
04/08/2011 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* |
04/08/2011 | ENGINEERING - FINAL | RDLD | Approved | |
04/11/2011 | NPPO - FINAL | JFEMLING | Approved | Approved |
04/11/2011 | LANDSCAPE - FINAL | JFEMLING | Approved | Approved |
04/12/2011 | SIGN - FINAL | JYBARRA | Approved | |
04/13/2011 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
04/18/2011 | PERMIT FINALED | JWEATHER | Approved |