Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address:
10673 E MIRA LN
Apply Date:
05/25/2010
Applicant:
N/A
Description:
NEW KITCHEN PAVILION BUILDING
Contractors:
  • DIVERSIFIED DESIGN AND CONSTRUCT

Permit Reviews

Permit Number - T10CM01431
Permit Status: C of o
Permit Description: NEW KITCHEN PAVILION BUILDING
Start Date Submittal Complete Date Status  
05/25/2010 PLANS OK TO SUBMIT - COMM 05/25/2010 COMPLETED Review Details
05/25/2010 3RD PARTY REVIEW-COMMERCIAL 07/01/2010 COMPLETED Review Details
07/01/2010 POST 3RD PARTY REVIEW 07/13/2010 COMPLETED Review Details
07/21/2010 3RD PARTY REVIEW-REVISION/OTHER 07/23/2010 COMPLETED Review Details
07/28/2010 REVISION - - 1ST 07/30/2010 COMPLETED Review Details
08/11/2010 REVISION - - 2ND 08/11/2010 COMPLETED Review Details
08/27/2010 3RD PARTY REVIEW-REVISION/OTHER 09/02/2010 COMPLETED Review Details
09/16/2010 3RD PARTY REVIEW-REVISION/OTHER 09/21/2010 COMPLETED Review Details
10/01/2010 3RD PARTY REVIEW-REVISION/OTHER 10/01/2010 COMPLETED Review Details
11/16/2010 REVISION - - 1ST 11/17/2010 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T10CM01431
Permit Status: C of o
Permit Description: NEW KITCHEN PAVILION BUILDING
Total Outstanding Activity Conditions - 1
Date Name
05/25/2010 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T10CM01431
Permit Description: NEW KITCHEN PAVILION BUILDING
Total Completed Inspections - 41
Date Description Inspector Results Comments
07/16/2010 ELECTRIC - UFER RJIROUDE Approved IVRS - Inspection :*
08/16/2010 PLUMBING - PRE SLAB RRICH Approved IVRS - Inspection :*
08/20/2010 BUILDING PRE-SLAB GDABBS Approved IVRS - Inspection :*
08/20/2010 STEM WALL/RETAINING WALL GDABBS Approved IVRS - Inspection :*
09/27/2010 FRAMING GDABBS Approved IVRS - Inspection :*
09/27/2010 ELECTRIC - INTERMEDIATE RJIROUDE Approved IVRS - Inspection :*
10/06/2010 PLUMBING - INTERMEDIATE RRICH Approved IVRS - Inspection :*
1) INTERCEPTOR TEST OK
10/06/2010 PLUMBING - SEWER HCS CONNECT RRICH Approved IVRS - Inspection :*
10/06/2010 PLUMBING - ROUGH, SOIL RRICH Approved IVRS - Inspection :*
10/06/2010 SITE - SEWER RRICH Approved IVRS - Inspection :*
10/21/2010 STUCCO MESH MHENSON Approved IVRS - Inspection :*
10/25/2010 SHEET ROCK NAILING GDABBS Approved IVRS - Inspection :*
11/16/2010 PLUMBING - YARD WTR LINE/TEST RRICH Approved IVRS - Inspection :*
11/19/2010 BUILDING ABOVE CEILING JBURGE Approved IVRS - Inspection :*
1) OK TO SET CEILING TILES
11/19/2010 PLUMBING - ABOVE CEILING RRICH Approved IVRS - Inspection :*
11/19/2010 ELECTRIC - CABLE DROP RJIROUDE Approved IVRS - Inspection :*
12/02/2010 PLUMBING - GAS PRESS TEST FNL RLEDONNE Approved IVRS - Inspection :*
12/17/2010 PLUMBING - GAS PRESSURE TEST RRICH Approved IVRS - Inspection :*
12/17/2010 ELECTRIC - FINAL RJIROUDE Approved IVRS - Inspection :*
12/17/2010 OUTDOOR LIGHTING FINAL RJIROUDE Approved IVRS - Inspection :*
12/17/2010 ELECTRIC - OUTDOOR LIGHTING RJIROUDE Approved IVRS - Inspection :*
12/17/2010 ELECTRIC - ABOVE CEILING RJIROUDE Approved IVRS - Inspection :*
12/23/2010 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
1) OK FOR FINAL
12/23/2010 MECHANICAL - HOOD SYSTEMS JMILITEL Approved IVRS - Inspection :*
12/23/2010 MECHANICAL - HOODS JMILITEL Approved IVRS - Inspection :*
12/23/2010 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
12/23/2010 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
12/23/2010 ENGINEERING - FINAL DROBERTS Approved THE CONTRACTOR HAS COMPLETED 95% OF THE SITE WORK BUT WILL NOT HAVE THE REMAINDER OF THE WORK COMPLETED TILL NEXT WEEK. THIS INSPECTION WILL BE RESCHEDULED ONCE ALL OF THE WORK IS FINISHED.
12/23/2010 NPPO - FINAL DROBERTS Approved
12/23/2010 BUILDING - PROGRESS GDABBS Approved IVRS - Inspection :*
12/23/2010 ROOF NAILING GDABBS Approved IVRS - Inspection :*
12/23/2010 REINFORCED MASONRY PRE-GROUT GDABBS Approved IVRS - Inspection :*
12/23/2010 EXCAVATION/LAYOUT REBAR & ZON GDABBS Approved IVRS - Inspection :*
12/23/2010 PLUMBING - FINAL RRICH Approved IVRS - Inspection :*
12/23/2010 SIGN - FINAL JYBARRA Approved
12/28/2010 RIGHT OF WAY - FINAL MCASTRO Approved
12/29/2010 BUILDING - FINAL GDABBS Approved IVRS - Inspection :*
1) ALL TRADE FINALS APPROVED PEDNDING FIRE DEPT.-FIRE ALARM APPROVAL-OK TO APPLY FOR TCO-FIRE DEPT REQUIRING FIRE WATCH UNTIL FIRE ALARM APPROVED
12/29/2010 LANDSCAPE - FINAL DLROBERTS Approved
12/29/2010 FIRE - FINAL DRamirez Approved Partial approval 12/29/10
1.) Life/Safety CofO fire inspection OK
2.) Code requiers that two phone lines be provided to monitor Fire Alarm System
3.) TCO permitted providing that a "Fire Watch" be in place when the school is back in session
4.) Need documentation from State inspector that the "Exhaust Hood System" was tested and approved.
5.) OK for Temporary Cof O
02/01/2011 FIRE - KITCHEN EXH HOOD FINAL DRamirez Approved This was approved by the State Fire Marshal's Office
02/01/2011 FIRE - ALARM FINAL DRamirez Approved Approval 2/1/11

Documents

File Name Document Type  
C OF O_02-04-2011.TIF CERT OF OCC VIEW
001_1P1.1.TIF CONSTRPLANS VIEW
002_3P1.1.TIF CONSTRPLANS VIEW
003_FS 1.0.TIF CONSTRPLANS VIEW
004_FS 2.0.TIF CONSTRPLANS VIEW
005_FS 3.0.TIF CONSTRPLANS VIEW
006_FS 4.0.TIF CONSTRPLANS VIEW
007_FS 4.1.TIF CONSTRPLANS VIEW
008_FS 4.2.TIF CONSTRPLANS VIEW
009_FS 4.3.TIF CONSTRPLANS VIEW
001_ROOF FRAMING PLAN.TIF CONSTRPLANS VIEW
001_G1.2.TIF CONSTRPLANS VIEW
002_X1.1.TIF CONSTRPLANS VIEW
001_1M1.1.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW