Permit: T10CM01430
Permit Details
Apply Date:
05/25/2010
Applicant:
N/A
Description:
NEW MIDDLE SCHOOL
Contractors:
- DIVERSIFIED DESIGN AND CONSTRUCT
Permit Reviews
Permit Number - T10CM01430
Permit Status: C of o
Permit Description: NEW MIDDLE SCHOOL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/25/2010 | PLANS OK TO SUBMIT - COMM | 06/30/2010 | COMPLETED |
06/30/2010 | POST 3RD PARTY REVIEW | 07/12/2010 | COMPLETED |
07/12/2010 | RESUBMITTAL | 07/13/2010 | COMPLETED |
07/28/2010 | REVISION - - 1ST | 07/30/2010 | COMPLETED |
09/16/2010 | 3RD PARTY REVIEW-REVISION/OTHER | 09/21/2010 | COMPLETED |
10/01/2010 | 3RD PARTY REVIEW-REVISION/OTHER | 10/01/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM01430
Permit Status: C of o
Permit Description: NEW MIDDLE SCHOOL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
05/25/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM01430
Permit Description: NEW MIDDLE SCHOOL
Total Completed Inspections - 39
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/20/2010 | ELECTRIC - UFER | RJIROUDE | Approved | IVRS - Inspection :* |
08/10/2010 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* |
08/10/2010 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
08/16/2010 | SITE - SEWER | RRICH | Approved | IVRS - Inspection :* 1) FROM TAP OF MAIN BACK THRU CLEANOUTS AND TO 5' FROM BLDG 2) 2 1/2" RECLAIMED FROM 5' FROM BLDG TO 40' FROM METER |
08/17/2010 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
09/13/2010 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
09/28/2010 | STUCCO MESH | GDABBS | Approved | IVRS - Inspection :* |
10/13/2010 | FRAMING | MHENSON | Approved | IVRS - Inspection :* |
10/25/2010 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
11/03/2010 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
11/18/2010 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* PROVIDE OVERFLOW SENSOR FOR THE SPLIT SYSTEM CONDENSATE. FINISH CONNECTIONS. LEAVE OUT TILES IN THIS AREA. WILL CHECK ON FINAL. |
11/18/2010 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
11/19/2010 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO SET CEILING TILES |
11/19/2010 | ELECTRIC - CABLE DROP | RJIROUDE | Approved | IVRS - Inspection :* |
11/19/2010 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
11/23/2010 | PLUMBING - GAS PRESSURE TEST | RRICH | Approved | IVRS - Inspection :* |
12/16/2010 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
12/16/2010 | OUTDOOR LIGHTING FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
12/16/2010 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
12/16/2010 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
12/23/2010 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR FINAL |
12/23/2010 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
12/23/2010 | NPPO - FINAL | DROBERTS | Approved | |
12/23/2010 | BUILDING - PROGRESS | GDABBS | Approved | IVRS - Inspection :* |
12/23/2010 | REINFORCED MASONRY PRE-GROUT | GDABBS | Approved | IVRS - Inspection :* |
12/23/2010 | STEM WALL/RETAINING WALL | GDABBS | Approved | IVRS - Inspection :* |
12/23/2010 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* |
12/23/2010 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
12/23/2010 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
12/23/2010 | PLUMBING - GAS PRESS TEST FNL | RRICH | Approved | IVRS - Inspection :* |
12/23/2010 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* |
12/23/2010 | SIGN - FINAL | JYBARRA | Approved | |
12/28/2010 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
12/29/2010 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* 1) ALL TRADE FINALS APPROVED-PENDING FIRE DEPT. FIRE ALARM APPROVAL-OK TO APPLY FOR TCO-FIRE DEPT. REQUIRING FIRE WATCH UNTIL FIRE ALARM SYSTEM APPROVED |
12/29/2010 | LANDSCAPE - FINAL | DLROBERTS | Approved | |
12/29/2010 | ENGINEERING - FINAL | DLROBERTS | Approved | |
12/29/2010 | FIRE - FINAL | DRamirez | Approved | Partial approvel 12/29/10 1.) Life/Safety inspection OK 2.) Visuals and audios for Fire Alarm System tested and approved. 3.) Unable to recieve "ground fault" or "circut disruption" signal on Fire panel. 4.) Need additional smoke detector in rooms #155 and #152. (too far from wall) 5.) Code requires that two telephone line be provided for the monitoring of the Fire Alarm System. 5.) TCO has been permitted provided that a "Fire Watch" is in place when the school is back in session. 6.) Order to establish Fire watch was issued 7.) OK for temporary Cof O |
01/19/2011 | FIRE - ALARM FINAL | DRamirez | Approved | Approved 1/19/11 |
01/27/2011 | PERMIT FINALED | JWEATHER | Approved |